SUMMARY INFORMATION
This presentation is for information purposes only and should be read in
conjunction with the most recent financial reports and other documents
lodged by Aeris with the Australian Securities Exchange (“ASX”) in
connection with its continuous disclosure obligations. This presentation
does not purport to contain all of the information that an investor should
consider when making an investment decision nor does it contain all of
the information which would be required in a product disclosure
statement or prospectus prepared in accordance with the requirements
of the Corporations Act.
No reliance should be placed on the information or opinions contained
in this presentation, which are provided as at the date of this
presentation (unless otherwise stated) and to the maximum extent
permitted by law, Aeris has no obligation to update the information
contained in this presentation. An investment in securities is subject to
known and unknown risks, some of which are beyond the control of
Aeris. Investors should consult with their own legal, tax, business and/or
financial advisors in connection with any acquisition of securities.
FINANCIAL INFORMATION
All financial information set out in this presentation is expressed in
Australian Dollars unless stated otherwise. Investors should be aware that
certain financial measures included in this presentation are “non-IFRS
financial information” under ASIC Regulatory Guide 230: “Disclosing nonIFRS financial information” published by ASIC and also “Non-GAAP
financial measures” within the meaning of Regulation G under the US
Securities Exchange Act of 1934 and are not recognised under the AAS
or IFRS. Aeris believes the non-IFRS financial information and non-GAAP
financial measures provide useful information to users in measuring the
financial performance and condition of Aeris.
However, investors should note that the non-IFRS financial information
and non-GAAP financial measures do not have standardised meanings
prescribed by AAS or IFRS. Therefore, the non-IFRS financial information is
not a measure of financial performance, liquidity or value under the IFRS
and may not be comparable to similarly titled measures presented by
other entities, nor should the information be construed as an alternative
to other financial measures determined in accordance with AAS or IFRS.
Investors are cautioned, therefore, not to place undue reliance on any
non-IFRS financial information included in this presentation.
FUTURE PERFORMANCE AND FORWARD-LOOKING STATEMENTS
This presentation contains certain ‘forward-looking’ statements, opinions
and estimates, which are based on assumptions and contingencies that
are subject to change without notice and involve known and unknown
risks and uncertainties beyond the control of Aeris and its officers. This
includes statements about market and industry trends, which are based
on interpretations of current market conditions.
Indications of, and guidance on, future earnings and financial position
and performance are forward-looking statements. As are statements
containing the words “expect”, “anticipate”, “estimate”, “intend”,
“believe”, “guidance”, “should”, “could”, “may”, “will”, “predict”, “plan”
and other similar expressions.
Forward-looking statements are based on information available to Aeris
as at the date of this presentation and should not be relied upon as an
indication or guarantee of future performance. Except as required by
law or regulation (including the ASX Listing Rules), none of Aeris, its
representatives or advisers undertakes any obligation to provide any
additional or updated information whether as a result of a change in
expectations or assumptions, new information, future events or results or
otherwise.
Investors are strongly cautioned against placing undue reliance on
forward-looking statements, especially considering the current economic
climate and significant volatility, uncertainty and disruption caused by
recent world events such as the COVID-19 pandemic and international
hostilities and associated economic changes.
DISCLAIMER
To the maximum extent permitted by law, Aeris and each of
its respective related bodies corporate, shareholders and affiliates, and
each of their respective officers, directors, partners, employees,
representatives, affiliates, agents, consultants and advisers (each a
“Limited Party”):
• expressly disclaim any and all responsibility and liability (including,
without limitation, any liability arising from fault, negligence or
negligent misstatement) for any direct, indirect, consequential or
contingent loss or damage arising from this presentation or reliance
on anything contained in or omitted from it or otherwise arising in
connection with this presentation;
• disclaim any obligations or undertaking to release any updates or
revisions to the information in this presentation and;
• do not make any representation or warranty, express or implied, as to
the accuracy, reliability, completeness or fairness of the information,
opinions and conclusions contained in this presentation or that this
presentation contains all material information about Aeris or the
Transaction or that a prospective investor or purchaser may require in
evaluating a possible investment in Aeris or acquisition of shares in
Aeris, or likelihood of fulfilment of any forward-looking statement or
any event or results expressed or implied in any forward-looking
statement.
PRODUCTION TARGETS CAUTIONARY STATEMENT
The Ore Reserve and Mineral Resource estimates underpinning the
Stockman Production Targets were prepared by a Competent Person in
accordance with the JORC Code 2012.
The material assumptions on which the Production Targets are based is
set out in Appendix C of the ASX Release of Aeris dated 28 April 2022
“Transformational Acquisition and Capital Raise” (Initial Report). Aeris
confirms that all material assumptions underpinning the production
targets in the Initial Report continue to apply and have not materially
changed. The modifying factors used in the estimation of the Ore
Reserve were also applied to the Mineral Resources in the generation of
the Production Targets.
2
Highlights for Q2 FY24
Copper equivalent production of 9.7kt for the quarter at AISC of
A$5.40/lb
Mt Colin mine production in line with plan although third-party ore
processing behind schedule leading to lower metal produced –
cash flow impacts mitigated by part payment for stockpiles
Tritton metal production impacted by labour and equipment
availability
Stockman feasibility study update released – focus on revised
processing flowsheet
Updated Mineral Resource estimate for Avoca Tank (Tritton)
increasing copper grade by 35% and contained copper metal by
16%
Jaguar on care and maintenance – restart studies underway
Gold production and costs at Cracow in line with plan
Successful $30 million equity raise to provide general working capital
and strengthen the balance sheet
Cracow TSF lift completed in early January ahead of schedule and
under budget
FY24 guidance maintained
3
Aeris Resources
Australian mid-tier, base and precious metals producer
Mt Colin Mine (100%)
Mine Type
FY24 Production Guidance
U/G Cu, Au
8kt - 10kt Cu
Cracow Operations (100%)
U/G Au
38koz - 48koz Au
Mine Type
FY24 Production Guidance
Barbara Project (100%) – Development
Mine Type
Resource1
U/G Cu, Au
45kt Cu
Jaguar Operations (100%) Care and Maintenance
Mine Type
Resource2
North Queensland
U/G Zn, Cu, Ag, Au
455kt Zn, 97kt Cu
Cracow
Jaguar
Tritton
Stockman Project (100%) – Developmemt
Mine Type
Resource2
Tritton Operations (100%)
U/G Zn, Cu, Au
624kt Zn, 315kt Cu
Mine Type
FY24 Production Guidance
U/G Cu
19kt - 24kt Cu
Stockman
1.
2.
Refer to ASX release “Barbara Mineral Resource Update” 28 June 2023.
See ASX announcements “Group Mineral Resource and Ore Reserve Statement” dated 18 April 2023 ,“Correction - Jaguar Deposit
Mineral Resource Update” dated 12 July 2023 and “Currawong and Wilga Deposits Mineral Resource Updates” dated 17 Jan 2024
4
Tritton
NSW
Q2 results
Performance impacted by labour and equipment
Sep 23
Dec 23
Qtr
Qtr
FY24
Guidance
kt
5.2
4.8
19 – 24
Gold Produced
koz
1.0
1.2
6–7
Silver Produced
koz
36.9
39.2
148 – 185
Mining
A$M
25.3
25.1
113 – 136
Processing
A$M
8.7
6.8
31 – 37
Site G&A
A$M
5.1
3.9
22 – 27
TC/RCs
A$M
5.4
4.6
19 – 23
Updated Mineral Resource for Avoca Tank increasing
copper grade by 35% and contained copper metal by 16%
Product Handling
A$M
3.3
3.8
16 – 20
Sustaining Capital
A$M
17.2
13.5
57 – 69
Completion of 6 hole drill program at Constellation
successfully extending known mineralisation along strike
and down plunge
Growth Capital
A$M
3.0
1.3
10 – 12
Exploration
A$M
0.6
0.7
7–9
Total copper production of 4.8kt at AISC of A$5.37
Production Summary
Unit
Labour and equipment availability impacted production –
being addressed with recruitment activities and additional
rental equipment
Copper Produced
Mining forecast to improve in second half FY24 with
increased contributions from the high grade Avoca Tank
and Budgerygar mines
Jameson cell optimisation continuing – 2% concentrate
grade improvement since commissioning
Cost Summary
6
Avoca Tank
Updated Mineral Resource Estimate
Updated MRE1 of 720kt at 3.4% Cu and 1.1g/t Au
35% increase in copper grade and 16% increase in
contained copper metal
Mineralised system remains open down-plunge with
significant potential to increase resource with further drilling
Complex resource shapes require increased grade control
drilling early in the mine life but will reduce over time
Cross section view (A) and long section view (B) showing the Avoca Tank MRE by resource
classification looking northwest and southwest respectively (green – Indicated, blue –
Inferred)
1.
Refer to ASX announcement “Avoca Tank Mineral Resource Update” dated 25th October 2023
7
Cracow
Queensland
Q2 results
Cracow production and costs to plan
Gold production of 11.1koz at AISC of A$2,407/oz, in line
with plan
Operating and capital costs on track
Sep 23
Dec 23
Qtr
Qtr
FY24
Guidance
koz
12.7
11.1
38 - 48
koz
12.8
11.4
Mining
A$M
15.0
13.0
50 - 60
Processing
A$M
6.4
5.9
26 - 31
Site G&A
A$M
2.7
3.0
12 - 15
Sustaining Capital
A$M
2.0
2.8
18 - 22
Growth Capital
A$M
7.1
8.2
23 - 28
Exploration
A$M
1.1
0.7
4-5
Production Summary
Unit
Gold Produced
Gold Sold
Cost Summary
Tailings dam lift completed in January, ahead of schedule
and under budget, extending the life of the operation
9
Near mine exploration
Targeting high-grade resource additions in the current
mining area
Exploring 5 priority targets in the Western Vein Field
Drill results exceeded expectations from early-stage exploration
Significant results1 include:
• 0.8m at 4.12g/t Au (Killarney Deeps)
• 1.7m at 2.75g/t Au (Coronation West)
• 0.4m at 8.42g/t Au (Emu)
• 0.4m at 1.27g/t Au (Emu)
• 0.4m at 3.04g/t Au (Bazsickle)
Follow up drilling planned in Q3
1. Refer to December 2023 Quarterly Report for more information. All intersections shown are true thickness estimates.
10
Mt Colin
North Queensland
Q2 results
Mining performing well and working capital managed
through part payment on stockpiles
Copper production of 1.6kt at AISC of A$5.38/lb
Mining operations ahead of plan due to strong
performance from the “cave” zone
Only one of the two processing runs originally scheduled
was completed, resulting in copper production below plan
To assist with working capital management Glencore has
agreed to undertake monthly part payment on stockpiles,
in between processing runs
Ore stockpiles of 133kt at quarter end yet to be processed
Sep 23
Dec 23
Qtr
Qtr
FY24
Guidance
kt
2.4
1.6
8 - 10
koz
1.1
0.8
4-5
Mining
A$M
10.9
9.2
34 - 41
Processing
A$M
5.9
5.8
25 - 30
Site G&A
A$M
1.7
1.1
7-8
TC/RCs
A$M
1.8
1.2
7-9
Product Handling
A$M
1.9
1.2
7-9
Sustaining Capital
A$M
(0.1)
-
0
Exploration
A$M
0.5
0.2
0
Production Summary
Unit
Copper Produced
Gold Produced
Cost Summary
12
Jaguar
Western Australia
Q2 results
Jaguar now focused on restart studies
Operation now on care and maintenance
Pre-feasibility study on restart options underway examining
increased ore production rates, maximised mill throughput
and improved metal recovery
Exploration activities focused on gold prospectivity of
tenement package
Sep 23
Dec 23
Qtr
Qtr
FY24
Guidance
kt
3.1
-
1.2 - 1.5
Copper Produced
kt
0.6
-
0.2 - 0.3
Gold Produced
koz
0.4
-
0.2 - 0.3
Silver Produced
koz
84
-
33 - 42
Mining
A$M
8.8
1.5
5-6
Processing
A$M
7.8
(0.2)
3-4
Site G&A
A$M
3.4
2.4
2-3
TC/RCs
A$M
4.3
(2.2)
2-3
Product Handling
A$M
2.0
0.1
1-2
Sustaining Capital
A$M
2.7
-
1–2
Growth Capital
A$M
-
-
1–2
Exploration
A$M
0.5
0.1
1–2
Production Summary
Unit
Zinc Produced
Cost Summary
14
Stockman Project
Victoria
Q2 Activities
Updates released on Mineral Resource and feasibility
study
Updated Mineral Resource estimates1 for Currawong and Wilga
deposits increased contained copper by 6%
Mine plan involving 12 years of ore production solely from Currawong
at 850ktpa rate2
Complex metallurgy, however, impacts metal recoveries and
processing costs
Investigating alternative processing flowsheet utilising ultrafine
grinding and the Albion Process
• Onsite production of a clean Cu concentrate and a bulk
Cu/Zn/Au/Ag concentrate
• Bulk concentrate trucked to a regional offsite location for
further processing with the Albion Process
Completion of feasibility study targeted for second half 2024
Currawong mine design
All primary approvals for mining and onsite processing in place
1.
2.
Refer to ASX announcement “Stockman Project – Currawong and Wilga Deposits Mineral Resource Update”
dated 17 January 2024
Refer to ASX announcement “Stockman Feasibility Study Update” dated 24 January 2024 for more information
and for the material assumptions underpinning the production target
16
Corporate
Closing cash and receivables increased to $44.7 million with cash of
$22.7 million
Sep
Dec
2023
2023
Qtr
Qtr
Closing cash
21.9
22.7
Jaguar - concentrate receivables
11.5
-
Mt Colin
1.6
5.5
Cracow - gold dore
0.3
0.1
Tritton - concentrate receivables
8.1
16.4
Useable Cash and Receivables
43.4
44.7
(A$ Million)
Completed $30 million equity raise to provide general working capital
Trade payables and other creditors balance reduced by $33.5 million
since 30 June 2023 to $87.3 million
Debt position of $40 million unchanged
Non-executive director, Sylvia Wiggins, resigned
17
Focus - next 6 months
Tritton improving production due to Avoca tank and Buderygar
ramp up
Complete mining at Mt Colin – Barbara study underway
Drilling to continue at Constellation – feasibility study update Q1
FY25
Stockman test work for alternate flowsheet and feasibility update
second half 2024
Cracow Golden Plateau drilling – resource definition for future
mining
Jaguar restart study complete second half 2024
Western Vein Field drilling continue to extend mine life
Burnvoir appointed to assist with refinancing options
18
Aeris Resources
Australian mid-tier, base and precious metals
producer
3 producing operations + 1 care & maintenance
1 long life development project
Highly prospective for further discoveries
FY24 production of 40 - 50kt Cu eq1
Substantial copper metal inventory
Excellent platform for growth
1.
Based on average commodity pricing of Cu US$8,725/t, Zn US$2,415/t, Au US$1,930/oz, Ag US$23.45/oz
19
Thank You
Share your feedback
Discover