GOLDEN PLATEAU PROJECT UPDATE
Released
Released
Announcement PDF
29 SEPTEMBER 2025
ASX/MEDIA RELEASE
GOLDEN PLATEAU PROJECT UPDATE
Large volume of mineralisation identified around the historical
underground workings extending down to 150m below the bottom
of the existing pit
Grade model1 developed on large amount of historic data2 to
assist with next phase of exploration
~7,000m diamond drill program planned to test extensions to
mineralisation below and along strike from the current pit
Drilling to support the release of an Exploration Target
Established Australian copper-gold producer and explorer, Aeris Resources Limited
(ASX: AIS) (Aeris or the Company) is pleased to provide an update on activities at
the Golden Plateau deposit, located within the Company’s 100% owned Cracow
tenement package in Queensland.
Aeris’ Executive Chairman, Andre Labuschagne, said “The historical production
from the Golden Plateau area highlights the significance of this mineralised system.
We are highly encouraged by the potential impact this near-term ore source could
have on extending the Cracow life-of-mine plan. Aeris is prioritising exploration at
Golden Plateau with the drill program to be completed this financial year.”
1 Grade model developed for internal planning only. The grade model is not JORC 2012 compliant and does not represent
either a Mineral Resource or Ore Reserve.
2 Refer to ASX announcement “Quarterly Activities Report – June 2025” dated 21 July 2025. All relevant JORC Table 1
documentation for the historical (pre 2020) drill hole data is listed in this document.
Aeris Resources Limited ABN 30 147 131 977
Level 6, 120 Edward Street, Brisbane QLD 4000 Australia
E: info@aerisresources.com.au T: +61 7 3034 6200
aerisresources.com.au
ABN 30 147 131 977
ABN 30 147 131 | Page1 977
Background
The Golden Plateau deposit is located within current mining leases, 1km north from
the Cracow Processing Facility and 2km east from current underground mining
operations at the Western Vein Field (Figure 1). The deposit is situated along a
regional northwest trending structural corridor, traced over a 7-10km strike length,
with anomalous gold mineralisation identified along most of the prospective
corridor. The Golden Plateau deposit is located at a major inflection (dilational jog)
along the regional structure, where it changes orientation to an east-west trend.
Figure 1 – Location map showing the Cracow Goldfield including the Golden Plateau deposit,
Western Vein Field and the Cracow Processing Facility.
2|P a g e
The Golden Plateau deposit is the most significant contributor to the known Cracow
goldfield in terms of ounces, with approximately 850koz 3 produced to date. Mining
(underground) began in the early 1930s and continued until 1976. Production over
this period totaled approximately 1.55Mt at 11.9g/t Au for 590koz Au 4, over eight
levels to a maximum depth of 260 m below surface.
Following a short hiatus, open pit mining commenced in 1987 and continued
through to 19903, targeting lower-grade mineralisation surrounding the previously
mined high-grade shoots. The pit advanced to approximately 120m below surface
and mined through the upper three underground levels, producing 2.2Mt at 2.7g/t
Au for 180koz Au3. Toward the end of the open pit operation, a brief phase of
underground mining occurred along the NS12 structure on the northeastern portion
of the deposit with reported production of ~46kt at 9.4g/t Au for 14koz Au.
A review of prospectivity at Golden Plateau is well advanced to assess the gold
potential within the mine footprint. Previous Aeris drill programs focused on structures
south of the historical workings (Chas, King and Harry's lode) and a shallow lode on
the western margin of the deposit (Western lode)5. The primary focus of the drill
programs was to delineate discrete high-grade structures for extraction via
underground mining methods.
The current review focuses on understanding the potential for a broader, low-grade
gold system that could support a larger-scale open-pit mining operation.
Geology
An updated geological interpretation has been completed within the historical
footprint, developed from detailed close-spaced paper sectional interpretations
and more than 1,200 drill holes across the Golden Plateau mine footprint
(combination of diamond and RC)6. A total of 33 mineralised lodes were modelled,
representing a range of different geometries and dimensions, suggestive of a
complex structural regime (Figure 2).
3 ~850koz production from Golden Plateau includes the production figures quoted above, in addition to production from
the CEX and Golden Mile pits, both located within 1km from the Golden Plateau mine footprint.
4 Vigar, A.J, 1994 Grade Modelling Reconciled to Open Pit Mining at the Golden Plateau Mine, Cracow, Queensland. AuslMM
Student Conference, April 1994, pp. 49-54.
5 Refer to ASX announcements “Cracow Gold Operations – Golden Plateau project update” dated 20 April 2022, “Highgrade gold intersections at Golden Plateau” dated 2 June 2022, “Golden Plateau drilling program update” dated 21 July
2022, “Golden Plateau drilling program update” dated 4 October 2022.
6 Refer to ASX announcement “Quarterly Activities Report – June 2025” dated 21 July 2025. All relevant JORC Table 1
documentation for the historical (pre 2020) drill hole data is listed in this document.
3|P a g e
Figure 2 – Plan view and long section view (looking north) showing the historical mine workings,
mineralised lodes and drill hole coverage across the Golden Plateau deposit.
4|P a g e
The structural history at Golden Plateau is complex, with a range of different
structural orientations interpreted. The development of higher grade shoots is
thought to occur at the intersection between different orientated structural
lineaments and exhibit a long down-plunge dimension and shorter strike extents
(based on modelled historical stopes).
A limitation of the historical drill hole data is that many were selectively sampled,
focused on assaying veins that were visually thought to contain high-grade. This
introduces bias and makes it difficult to fully quantify the in-situ gold content from
the existing dataset.
To help refine drill targeting and understand areas with increased potential, the
Company developed an internal, non-JORC 2012 compliant grade model. The
grade model highlights a large volume of mineralisation around the historical
underground workings extending up to 150m below the bottom of the pit (2,200mRL
level). The grade model is used as an internal guide to highlight prospective areas
for follow-up drilling. Importantly, it does not represent a Mineral Resource or Ore
Reserve under JORC 2012 but serves as an internal planning tool to focus the next
round of drilling.
5|P a g e
Figure 3 – Cross sections looking east at 1885mE and 2208mE showing the current mine workings,
drill hole traces (displaying gold grades) and the non-JORC compliant grade model.
6|P a g e
Planned Drill Program
An approximate 7,000 metre diamond drill program is designed to address
information gaps by:
Collecting representative samples through mineralised lodes, including
twinning historical high-grade intersections;
Collecting geological information to further refine and improve the geology
model/understanding;
Confirm/validate the current void model;
Collecting geotechnical information as inputs to geotechnical design
parameters;
Collecting representative samples for metallurgical test work to support the
determination of recovery factors applicable to the Cracow process plant;
Collecting geochemical samples for waste rock characterisation to support
the evaluation of potential environmental waste dump planning options.
The planned drilling program is designed to update the geological model in support
of defining a JORC-compliant Exploration Target. While there is a significant amount
of historical drilling data within the Golden Plateau mine footprint, much of it does
not meet the requirements of the JORC Code (2012), particularly with regard to
QA/QC protocols and assay representativity. Upon completion of the drilling
program, the data will be assessed to determine what additional drilling is required
to support the development of a Mineral Resource. Any new Mineral Resource
defined will be incorporated into the existing reported Mineral Resource for Golden
Plateau7.
7 Refer to ASX announcement “Group Mineral Resource and Ore Reserve statement” dated 22 July 2025.
7|P a g e
Figure 4 – Plan view showing the planned drill traces across the Golden Plateau deposit.
This announcement is authorised for lodgement by:
Andre Labuschagne
Executive Chairman
ENDS
For further information, please contact:
Andre Labuschagne
Executive Chairman
Tel: +61 7 3034 6200
Stefan Edelman
General Manager – Corporate Development
investorrelations@aerisresources.com.au
or visit our website at www.aerisresources.com.au
8|P a g e
About Aeris
Aeris Resources is a mid-tier base and precious metals producer. Its copper dominant portfolio
comprises two operating assets, multiple development projects and a highly prospective exploration
portfolio. Aeris has a strong pipeline of organic growth projects and an aggressive exploration
program and continues to investigate strategic merger and acquisition opportunities. The
Company’s experienced board and management team bring significant corporate and technical
expertise to a lean operating model. Aeris is committed to building strong partnerships with its key
community, investment and workforce stakeholders.
Previous Information
The information in this announcement that relates to previously reported exploration results for the
Golden Plateau deposit is extracted from ASX announcements all of which are available on the
company’s website at www.aerisresources.com.au. The company confirms that it is not aware of
any new information or data that materially affects the exploration results included in the relevant
original market announcements. The Company confirms that the form and context in which the
Competent Person and Qualified Person’s findings are presented have not been materially modified
from the relevant original market announcements.
Competent Persons Statement – Exploration Results
Mr Craig Judson confirms that he is the Competent Person for all Exploration Results at the Cracow
Operation, and he has read and understood the requirements of the 2012 Edition of the Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code, 2012
Edition). Mr Judson is a Competent Person as defined by the JORC Code, 2012 Edition, having
relevant experience to the style of mineralisation and type of deposit described in the Report and to
the activity for which he is accepting responsibility. Mr Judson is a Member of the Australasian Institute
of Mining and Metallurgy (MAusIMM No. 325510). Mr Judson has reviewed the Report to which this
Consent Statement applies and consents to the inclusion in the Report of the matters based on his
information in the form and context in which it appears. Mr Judson is a full-time employee of Aeris
Resources Limited.
9|P a g e