QUARTERLY ACTIVITIES REPORT - MAR 2026
Released
Released
Announcement PDF
Aeris Resources Limited 1
Quarterly Activities Report
Quarterly Activities Report
For the period ended 31 March 2026
Highlights
• Cash and receivables of $149.8 million, up from $106.4 million (Dec 25)
• Strong cash flow from operations of $75.8 million for the quarter, up 72%
• Group copper equivalent production of 10.4kt1 for Q3 at AISC of A$4.86/lb Cu eq
• Cracow – gold production of 10.1koz on plan
• Tritton – copper produced of 5.3kt was slightly below the revised plan mainly due
to lower grade mined from both underground and open pit
• Tritton – Murrawombie Pit delivering Stage 2 ore with mill running at nameplate
capacity
• Costs well managed across the group, with limited diesel pricing impacts
• Constellation Project – early works to commence in Q4 to derisk FY27
• Golden Plateau exploration program expanded with drilling returning multiple
high-grade intersections
• Aeris to acquire the South Cobar Copper Project from Peel Mining to create a long-
life copper mining hub in the Cobar region
Unit
Sep 25
Qtr
Dec 25
Qtr
Mar 26
Qtr
YTD
FY26
Guidance
Safety – LTIFR /mmhr 1.3 1.2 3.5
Copper produced kt 6.1 5.0 5.3 16.5 24 – 29
Gold produced koz 10.9 12.9 12.3 36.1 44 – 56
Silver produced koz 72.2 50.3 61.7 184.2 240 – 293
Cu eq production1 kt 10.3 10.1 10.4 30.7 40 – 49
Operating Costs
Total mine operations A$M 79.0 73.1 84.0 236.1 302 – 369
Corporate A$M 6.4 5.1 5.9 17.4 21 – 26
Care & maintenance A$M 2.6 2.6 3.3 8.4 6 – 7
Capital Costs
Sustaining A$M 16.6 18.6 17.7 52.9 57 – 70
Growth & projects A$M 31.6 25.6 21.6 78.7 65 – 80
Exploration A$M 3.4 1.6 5.6 10.7 18 – 23
AISC2 A$M 105.0 93.4 110.8 309.2
AISC
A$/lb
Cu eq
4.64 4.21 4.86 4.57
1 Cu Eq t = ((Cu Produced x Cu $/t) + (Au Produced x Au $/oz) + (Ag Produced x Ag $/oz)) / (Cu $/t)
Assumed average commodity prices FY26: US$9,429/t Cu, US$3,241/oz Au, US$35/oz Ag. Q1 prices: US$9,792/t Cu,
US$3,454/oz Au, US$39/oz Ag. Q2 prices: US$11,100/t Cu, US$4,146/oz Au, US$55/oz Ag. Q3: US$12,852/t Cu,
US$4,877/oz Au, US$84/oz Ag. Aeris confirms that it is the Company’s opinion that all the elements included in the
metal equivalents calculation have a reasonable potential to be recovered and sold.
2 AISC excludes care and maintenance costs
2
Group Safety, Environment and Community
During the quarter, three Lost Time Injuries (LTIs) occurred. These involved a
musculoskeletal injury related to vehicle access, a hand injury during cable handling,
and an eye injury resulting from contact with grout. Each incident was investigated,
with corrective actions implemented.
At Cracow, an environmental incident was reported to the regulator during the
quarter. The notification related to water release following a significant rainfall event,
which exceeded available storage and transfer capacity on site.
Figure 1: Group LTIFR1
1 An injury in December 2025 was subsequently reclassified as an LTI
-
1
2
3
4
LTI LTIFR
3
Tritton Operations (NSW)
Key points for quarter:
• Ore mined for the quarter was strong with a 62% increase in tonnes mined
compared to prior quarter
• Murrawombie Pit now delivering Stage 2 ore, with Tritton running at nameplate
milling capacity in Q4, and 63kt stockpiled on the ROM at the end of the quarter
• Production of 5.3kt Cu at AISC of A$4.53/lb, slightly below plan due to lower grade
• FY26 production forecast to be within the low end of guidance
Production Summary Unit
Sep 25
Qtr
Dec 25
Qtr
Mar 26
Qtr
YTD
FY26
Guidance
Ore Mined kt 284.7 245.1 392.6 922.4
Mined Grade % Cu 1.98 2.16 1.49 1.82
Ore Milled kt 358.3 251.8 326.0 936.0
Milled Grade % Cu 1.80 2.08 1.74 1.85
Recovery % Cu 95.0 95.7 93.9 94.9
Copper Produced kt 6.1 5.0 5.3 16.5 24 – 29
Gold Produced koz 2.0 1.8 2.2 6.0 8 – 10
Silver Produced koz 72.2 36.6 55.5 164.3 215 – 263
Cost Summary
Mining A$M 28.0 27.2 32.1 87.3
Processing A$M 8.6 8.6 8.8 26.0
Site G&A A$M 6.1 6.3 6.5 18.8
TC/RCs A$M 1.5 1.2 1.5 4.2
Product Handling A$M 5.3 3.5 6.3 15.1
Total mine operations A$M 49.5 46.8 55.3 151.5 207 – 253
By-Product Credit A$M (14.8) (13.2) (22.9) (50.8)
Royalties A$M 3.6 3.0 4.6 11.2
Corporate G&A A$M 0.5 0.5 0.5 1.6
Inventory Movements A$M 4.0 (6.8) 2.4 (0.3)
Sustaining Capital1 A$M 14.3 13.2 13.2 40.8 39 – 48
All-In Sustaining Costs2
A$M 57.3 43.6 53.1 154.0
A$/lb 4.24 3.94 4.53 4.24
Growth Capital A$M 25.6 23.3 20.9 69.9 58 – 71
Exploration A$M 1.8 0.7 1.8 4.3 10 – 12
All-In Costs
A$M 84.7 67.6 75.9 228.2
A$/lb 6.27 6.12 6.48 6.29
1. Includes sustaining capital, capitalised mine development, rehabilitation and financing payments (principal
and interest) on leased assets
2. All-In Sustaining and All-In Costs are based on copper produced.
4
Operations
Ore mined for quarter was strong and above plan with 62% increase in tonnes mined
compared to prior quarter. Tritton achieved production of 5.3kt Cu in the March
quarter, up from the previous quarter. Copper produced was slightly below the
revised plan (plan was revised as a result of geotechnical issues reported in the
December quarter) mainly due to lower grade mined from both underground and
open pit.
The pit is now well within the Stage 2 ore, with 63kt stockpiled on the ROM at the end
of the quarter. The mill will be running at full capacity in Q4. Aeris forecasts FY26
production to achieve the lower end of the annual guidance range.
Recoveries for the quarter were slightly lower than plan, impacted by lower grade
transitional ore from Murrawombie Pit. Recoveries and grade have improved as
mining moved into the primary sulphide ore post quarter end.
Concentrate rail haulage volumes have returned to normal, with the concentrate
stockpile reported in the December quarterly now cleared. Product handling costs
were higher quarter-on-quarter, reflecting increased movements to clear the
stockpile along with elevated rail costs while the rail bridge is being rebuilt.
Management continues to closely manage any impact to concentrate rail haulage.
AISC was well managed although mining operating costs were higher than the
previous quarter due to a 62% increase in ore tonnes mined, and waste stripping no
longer being capitalised from the point that Murrawombie Pit commenced mining
Stage 2 ore. AISC was also impacted by inventory movements associated with the
increased movement of concentrate stockpiles outlined above.
Growth capital for the quarter was predominantly capitalised stripping at
Murrawombie Pit. No further growth capital is forecast for Murrawombie Pit in Q4.
The impact of increased diesel prices was minimal for Q3 although continued volatility
experienced in diesel pricing is expected to impact costs in Q4. There are currently no
diesel supply shortages expected. Management is currently actively working with
suppliers to ensure consistent supply and closely monitoring the situation.
The rehabilitation of the old Murrawombie heap leach pads is progressing on plan
(Figure 3).
5
Figure 2: Murrawombie Pit operation into Stage 2 ore
Figure 3: Rehabilitation of old heap leach pads at April 2026
6
Constellation Project
The Aeris Board has approved the commencement of early works construction for the
Constellation Project to support the Tritton life of mine. Initial activities scheduled to
begin in early May, include development of the haul road connecting the project site
to the Tritton processing plant, establishment of the services corridor, and site
establishment works.
A decision has been made to de-risk project development by bringing forward a
portion of planned capital expenditure from FY27 into Q4 FY26, predominantly
associated with the haul road and services corridor. This expenditure is outside existing
guidance and expected to be between $10 million and $15 million. Aeris intends to
fund the ongoing construction of the Constellation Project from operational cash
flows. Major project contracts are currently being finalised.
Recent optimisation studies support a revised development strategy comprising a
smaller, two-stage open pit, which will enhance cash flow and provide a more
consistent ore feed profile.
Environmental permitting and regulatory approvals remain on track. Mining leases are
anticipated to be granted in the June quarter, supporting the planned
commencement of open pit mining operations in the first quarter of FY27.
Exploration
Drilling activity continued across the Tritton operation during the quarter, with resource
definition and exploration drilling programs underway at the Avoca Tank, Budgerygar
and South Wing deposits. A detailed exploration update will be provided in Q4.
At Avoca Tank, diamond drilling continued to test extensions below and adjacent to
the current Mineral Resource1. Drilling has continued to intersect mineralisation
outside the boundaries of the current Mineral Resource. Whilst the program is ongoing
and will continue throughout Q4, work is now underway to complete an updated
Mineral Resource estimate at Avoca Tank.
At Budgerygar, drilling focused on resource definition to support conversion of the
current Inferred Mineral Resource to Indicated, as well as testing extensions below the
base of the current resource. Drilling has continued to intersect copper sulphide
mineralisation, with assay results being received progressively. One drill rig will continue
at Budgerygar with an updated Mineral Resource estimate expected to be
completed in Q4.
The South Wing deposit is located directly along strike from the Tritton deposit and in
close proximity to existing underground infrastructure. South Wing hosts an Inferred
Mineral Resource of 600kt @ 1.5% Cu2. The current resource definition drill program is
focused on upgrading the Inferred Mineral Resource to an Indicated classification.
1 Refer to ASX announcement “Group Mineral Resource and Ore Reserve Statement” dated 22nd July 2025
2 Refer to ASX announcement “Group Mineral Resource and Ore Reserve Statement” dated 22nd July 2025
7
Cracow Operations (QLD)
Key points for quarter:
• Gold production 10.1koz in line with plan at AISC of A$3,442/oz
• Costs well managed and on budget
• High grade drill results reported from Golden Plateau exploration drilling resulting
in expansion of the program to 14,000m
Production Summary Unit
Sep 25
Qtr
Dec 25
Qtr
Mar 26
Qtr
YTD
FY26
Guidance
Ore Mined kt 142.3 150.9 137.1 430.3
Mined Grade g/t 2.16 2.49 2.40 2.35
Ore Milled kt 154.3 157.3 155.3 466.9
Milled Grade g/t 1.98 2.43 2.23 2.22
Recovery Au 90.4% 90.5% 90.6% 90.5%
Gold Produced koz 8.9 11.1 10.1 30.1 36 – 46
Gold Sold koz 8.8 11.0 10.1 29.9
Cost Summary
Mining A$M 19.6 16.2 17.6 53.4
Processing A$M 7.2 7.1 7.7 22.0
Site G&A A$M 2.8 2.9 3.5 9.2
Total mine operations A$M 29.6 26.3 28.8 84.6 95 – 116
By-Product Credit A$M (0.5) (0.5) (0.7) (1.7)
Royalties A$M 2.6 3.7 3.6 9.9
Corporate G&A A$M 0.4 0.4 0.4 1.3
Inventory Movements A$M (1.9) 0.9 (1.8) (2.8)
Sustaining Capital1 A$M 2.3 5.4 4.4 12.1 18 – 22
All-In Sustaining Costs2
A$M 32.5 36.1 34.7 103.3
A$/oz 3,692 3,278 3,442 3,455
Growth Capital A$M 5.5 2.1 0.6 8.2 6 – 8
Exploration A$M 1.0 0.7 3.4 5.2 5 – 7
All-In Costs2
A$M 39.0 38.9 38.8 116.7
A$/oz 4,437 3,528 3,841 3,901
1. Includes sustaining capital, capitalised mine development, rehabilitation and financing payments (principal
and interest) on leased assets
2. All-In Sustaining and All-In Costs are based on gold sold
Operations
Cracow performed largely as forecast for the quarter with 10.1koz Au produced at
AISC of $3,442/oz. Cracow remains on track for mid-point of the guidance range.
All-in sustaining costs were up quarter-on-quarter due to lower gold ounces produced
but still in line with plan. Mining operating costs were higher due to increased
operating development but offset by lower capitalised development. Exploration
costs increased as drilling ramped up at Golden Plateau.
8
Exploration
Exploration drilling continued at the Golden Plateau deposit, located 1km from the
Cracow processing plant. Following successful results received to date, the drill
program has been expanded from 6,400m to approximately 14,000m. The drill
program is designed to test remnant mineralisation surrounding historical underground
workings as well as confirm the geology and void models.
A total of 32 holes have been completed with assays returned for 15 holes. High grade
results have been consistently reported across multiple lodes, increasing confidence
in the potential for Golden Plateau to become a significant new ore source for
Cracow. Figure 4 shows the modelled mineralised lodes along with planned and
completed drill holes.
Key intersections1 returned during the quarter include:
• GPS140 34.5m2 at 3.1g/t Au (South lode)
• GPS134 7.1m2 at 4.9g/t Au (West lode)
• GPS139B 6.8m2 at 4.2g/t Au (West lode)
• GPS130 5.0m2 at 12.7g/t Au (Ferneyside)
• GPS135 10.0m2 at 2.9g/t Au (Sunnyside)
The drill program will continue in Q4 FY26. Results will be incorporated into an updated
geological model to support open pit mine design and environmental permitting
assessments.
1 Refer to ASX releases Golden Plateau Drill Program More Than Doubled as High Grade Drill Results Continue, dated
30 March 2026, and Significant Gold Intersections from Golden Plateau Drilling, dated 9 February 2026 for more
information.
2 Estimated true thickness
9
Figure 4: Plan view of modelled mineralised lodes and current drill program at Golden Plateau
North Queensland (QLD)
Key points for quarter:
• Divestment completed in March for cash consideration of $5 million plus the
release of ~$6.5 million from cash backed environmental bonds
Jaguar (WA)
Key points for quarter:
• Operation transitioning to lower cost, essential care and maintenance phase
• Base metals exploration program commenced
Exploration
During the quarter, exploration at the Jaguar project continued to advance base
metal drill targets along the known prospective 10km volcanic-hosted massive
sulphide (VHMS) corridor (Figure 5).
10
Field activities included soil sampling to assist with defining gold targets and meeting
tenement commitments. Eight high-priority base metal targets have been defined
along a volcanic zone with reclassified stratigraphy, informed by a 2024-2025 regional
mapping campaign east of the known VHMS corridor. Targets comprise seven
geology and gravity anomalies and one geology and electromagnetic (EM) target,
with discrete gravity anomalies modelled at depths between 60m and 270m and
strike lengths of up to 1km. The gravity anomalies, in combination with pathfinder
anomalism from rock chip and soil sampling and the presence of pervasive sericite
alteration, are considered supportive of VHMS-style mineralisation within this newly
defined corridor.
Preparations for a first pass drill program commenced during the quarter, with testing
of the eight targets planned for Q4 FY26.
Figure 5: Jaguar base metal targets
11
Stockman Project (VIC)
Key points for quarter:
• Feasibility study updates underway. Targeting release in early FY27
• Community Reference Group meeting held, demonstrating strong community
and local government support
• Project holding costs remain minimal
Corporate
Cash and Receivables
At the end of the quarter, Aeris had increased useable cash and receivables of $149.8
million with a closing unrestricted cash balance of $119.1 million. Total restricted cash
held against bonds totalled $17.7 million.
(A$ Million)
Sep 25 Dec 25 Mar 26
Qtr Qtr Qtr
Closing Cash 32.0 87.9 119.1
Receivables
Tritton 14.4 18.4 30.7
Useable Cash and Receivables 46.4 106.4 149.8
Cash flow from operations was very strong for the quarter at $75.8 million, a 72%
increase quarter-on-quarter, supported by higher commodity prices.
(A$ Million)
Sep 25 Dec 25 Mar 26
Qtr Qtr Qtr
Opening cash 28.2 32.0 87.9
Cash flow from operations 53.1 44.0 75.8
Cash flow from capital expenditure (46.6) (43.8) (41.7)
Cash flow from financing (2.7) 55.8 (3.0)
Closing cash 32.0 87.9 119.1
12
Figure 6: Mar Quarter Cash Flow (A$M)
Finance and Other includes gold hedging
Debt and Hedging
During the quarter the company continued to deliver into the gold hedge on Cracow
production. At the end of the quarter, 5.5koz are left to be delivered by June 2026.
Acquisition of Peel Mining
On 12 February 2026, Aeris announced that it had entered into an agreement to
acquire Peel Mining’s South Cobar Copper Project via a scheme of arrangement.
Under the transaction, Aeris will acquire Peel Mining Limited for 0.3363 Aeris shares per
Peel share. Concurrently, Peel’s non-copper assets (including the Southern Nights
Complex) will be demerged into a new company via an in-specie distribution of its
shares to Peel shareholders.
The transaction represents a highly synergistic consolidation of Aeris’s Tritton
Operations with Peel’s South Cobar Copper Project, comprising the advanced Mallee
Bull and Wirlong deposits. It creates a long-life regional mining hub with significant
copper resources. The value of the South Cobar Copper Project is unlocked with
Tritton’s processing capacity and Aeris’s proven operational and development
capabilities.
13
Figure 7: Location of Peel's South Cobar Copper Project relative to Tritton
The transaction has been unanimously recommended by the Peel board of directors
and major Peel shareholder, Perth Capital Pty Ltd and its associates, is supportive of
the transaction. The shareholder meeting to approve the scheme and demerger is
expected to occur in mid-June 2026, with final implementation anticipated in early
July.
Authorised for lodgement by:
Andre Labuschagne
Executive Chairman
ENDS
For further information, please contact:
Andre Labuschagne Stefan Edelman
Executive Chairman General Manager – Corporate Development
Tel: +61 7 3034 6200 investorrelations@aerisresources.com.au
or visit our website at www.aerisresources.com.au
14
About Aeris
Aeris Resources is a mid-tier base and precious metals producer. Its copper dominant portfolio
comprises two operating assets, multiple development projects and a highly prospective
exploration portfolio.
Aeris has a strong pipeline of organic growth projects, an aggressive exploration program and
continues to investigate strategic merger and acquisition opportunities. The Company’s
experienced board and management team bring significant corporate and technical
expertise to a lean operating model. Aeris is committed to building strong partnerships with its
key community, investment and workforce stakeholders.
Competent Persons Statement
The information in this report that relates to Exploration Targets or Exploration Results at the
Cracow Operation is based on information compiled by Craig Judson. Mr Judson confirms that
he is the Competent Person for all Exploration Results, summarised in this Report and he has
read and understood the requirements of the 2012 Edition of the Australasian Code for
Reporting of Exploration Targets, Exploration Results, Mineral Resources and Ore Reserves
(JORC Code, 2012 Edition). Mr Judson is a Competent Person as defined by the JORC Code,
2012 Edition, having relevant experience to the style of mineralisation and type of deposit
described in the Report and to the activity for which he is accepting responsibility. Mr Judson
is a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM No. 325510). Mr
Judson has reviewed the Report to which this Consent Statement applies and consents to the
inclusion in the Report of the matters based on his information in the form and context in which
it appears. Mr Judson is a full-time employee of Aeris Resources Limited.