CORPORATE UPDATE AND FY24 GUIDANCE
Jaguar to be placed on care and maintenance in September due to
forecast operating losses in FY24:
― Operational challenges, particularly seismic events, in second
half of FY23 resulted in sub-optimal mine plans for FY24
― Decision preserves the in-ground value of the current ~8 million
tonne Mineral Resource1 across the Jaguar Operation
― Feasibility study to commence on a re-start strategy at higher
production rates
Group FY24 guidance of 40kt – 50kt Cu equivalent2 based on
increased Tritton production but minimal contribution from Jaguar
New, $50 million, non-dilutive 2 year working capital facility secured
with major shareholder, Washington H Soul Pattinson and will replace
the ANZ $20 million working capital facility
Established Australian copper-gold producer and explorer, Aeris Resources Limited
(ASX: AIS) (Aeris or the Company) is pleased to provide this corporate update.
Aeris’ Executive Chairman, Andre Labuschagne, said “We have made the tough
but appropriate decision to place the Jaguar Operation onto care and
maintenance, with operations ceasing in September. Between the operational
challenges, lower zinc price and cost inflation it became obvious that the best value
for our shareholders was to pause production at Jaguar. We firmly believe this
decision provides the greatest opportunity for shareholders to realise value from
Jaguar over the medium term.”
1 See ASX announcements “Group Mineral Resource and Ore Reserve Statement” dated 18 April 2023 and “Correction -
Jaguar Deposit Mineral Resource Update” dated 12 July 2023
2 Based on average commodity pricing of Cu US$8,725/t, Zn US$2,415/t, Au US$1,930/oz, Ag US$23.45/oz
Aeris Resources Limited ABN 30 147 131 977
Level 6, 120 Edward Street, Brisbane, QLD 4000, Australia
E: info@aerisresources.com.au T: +61 7 3034 6200
aerisresources.com.au
ABN 30 147 131 977
ABN 30 147 131 | Page1 977
“Jaguar has a significant metal inventory across four deposits, and an underutilised
processing plant. Leaving the metal in the ground until we have an optimised restart
plan, at higher production rates, was clearly the better alternative than continuing
a loss-making operation. We will now commence feasibility work on restart options.”
“FY24 production guidance is forecast to be 40kt – 50kt copper equivalent1 with
minimal contribution from Jaguar and down from 51.5kt2 in FY23. Of particular note,
Tritton copper production is forecast to increase significantly on the back of the
higher grade Avoca Tank and Budgerygar mines developed in FY23.”
“In order to wind-down Jaguar in an orderly manner whilst progressing our multiple
growth projects we have bolstered the Company’s working capital position with a
2-year, $50m secured loan from our major shareholder, Washington H Soul Pattinson
(WHSP), which replaces the ANZ $20 million Working Capital Facility. This facility
supports Aeris’ plans without dilution to shareholders and demonstrates WHSP’s
commitment to the business.”
Jaguar Update
Over the course of FY23, Jaguar was impacted by multiple factors. Operationally,
production was constrained by availability of stoping fronts and low development
rates in the Bentley mine. Lower production results have been compounded by cost
inflation along with a 20% decline in zinc price over the last two quarters.
The mine also experienced three mining induced seismic events in the last quarter,
which further disrupted production and prevented access to high-grade stopes. To
ensure safe operations can be maintained, Aeris has halted all operations in the
Bentayga mining area until further geotechnical assessments can be made.
The low development rates, due largely to equipment congestion and ventilation
constraints, mean that decline access to the Turbo deposit has also been delayed.
Without access to Turbo, ore production was forecast to drop considerably at the
end of Q1 FY24.
Under these operational and financial parameters, Jaguar was forecast to make a
significant operating loss in FY24. The decision to pause production at Jaguar and
place it on care and maintenance from September 2023 has been made to limit
cash outflows and preserve the considerable in-ground resource value.
Jaguar Operations will cease mining operations in August and complete processing
of ore stockpiles soon thereafter, at which point the operation will transition to care
and maintenance. The operation will remain on care and maintenance, at least
through FY24, until a restart can be justified at improved economics.
1 Based on average commodity pricing of Cu US$8,725/t, Zn US$2,415/t, Au US$1,930/oz, Ag US$23.45/oz
2 Based on average commodity pricing of Cu US$8,274/t, Zn US$3,060/t, Au US$1,840/oz, Ag US$21.07/oz
2|P a g e
There remains an ~8 million tonne Mineral Resource1 with a significant metal
inventory of copper, zinc, gold and silver across the four main deposits at Jaguar
Operations: Bentley (including Turbo), Jaguar, Triumph and Teutonic Bore. As well as
these deposits, Aeris has identified numerous exploration targets on the tenement,
prospective for VMS deposits and primary gold mineralisation.
Aeris continues to believe in the value and potential of the Jaguar Operation and
considers that in the right operating environment and with the right business plan it
will make a substantial positive financial contribution to the Aeris group. Studies will
now commence on a re-start strategy to exploit the multiple mineral resources at
higher production rates, targeting 600-700ktpa, to fill an upgraded mill and improve
operating cost efficiencies.
Group FY24 Guidance
Total FY24 copper equivalent production is forecast to be 40 - 50kt2, down from
51.5kt3 in FY23, with minimal contribution from Jaguar. Group level guidance is
shown in the following table. Guidance for each operation is provided in Appendix
1.
FY24
Guidance
FY23A
kt
kt
koz
koz
kt
28 - 35
1.2 - 1.5
48 - 60
181 - 227
40 - 501
27.4
22.5
59.6
884
51.52
Operating Costs
Mining
Processing
Site G&A
TC/RCs
Product handling
$M
$M
$M
$M
$M
202 - 243
84 - 101
43 - 52
28 - 34
24 - 29
259
105
69
40
36
Capital Costs
Sustaining
Growth
Exploration
Projects
$M
$M
$M
$M
76 - 91
34 - 41
12 - 15
2-3
83
45
15
6
Group
Production
Copper
Zinc
Gold
Silver
Copper equivalent
1 See ASX announcements “Group Mineral Resource and Ore Reserve Statement” dated 18 April 2023 and “Correction Jaguar Deposit Mineral Resource Update” dated 12 July 2023
2 Based on average commodity pricing of Cu US$8,725/t, Zn US$2,415/t, Au US$1,930/oz, Ag US$23.45/oz
3 Based on average commodity pricing of Cu US$8,274/t, Zn US$3,060/t, Au US$1,840/oz, Ag US$21.07/oz
3|P a g e
Copper production at Tritton is forecast to grow from 17.2kt in FY23 to 19kt – 24kt in
FY24, due to the increased availability of high-grade mining areas, particularly at
Avoca Tank and Budgerygar. Growth capital at Tritton will reduce significantly as
the new mines move into sustaining production.
At the North Queensland operations, the Mt Colin mine is forecast to produce 8kt –
10kt copper. As demonstrated in FY23, achieving copper production targets also
requires third-party operators to meet scheduled processing runs. No capital
expenditure is planned for North Queensland, other than minor exploration.
Cracow production guidance for FY24 is for 38koz – 48koz Au. Cracow will be
investing significant growth capital on a tailings dam lift in the first half of FY24 to
add an additional 3 years capacity as well as developing an exploration decline to
improve drilling access to the Golden Plateau deposit.
Production at Jaguar will be limited and scheduled to cease during August. Capital
costs will include those associated with the dewatering of the Jaguar mine and
further technical studies.
Aeris is maintaining its focus on operating costs across the portfolio although cost
inflation is still a challenge for most major consumables.
Funding
Cash flow for the final quarter of FY23 has been impacted by the reduced
production out of Jaguar and deferral of the Mt Colin processing run in June, along
with lower zinc prices and general cost inflation across the business.
The first half of FY24 will not only include closure costs (payment of creditors and
workforce separation costs) related to Jaguar but also $18 million capital investment
on a new tailings facility at Cracow and re-commencement of resource drilling at
the Constellation deposit.
To ensure sufficient working capital liquidity to deliver on FY24 plans, Aeris has
secured a $50 million working capital facility (Facility) with its major shareholder,
Washington H Soul Pattinson (WHSP). The Facility is non-dilutive to shareholders, with
no equity or production-linked components. The WHSP Facility will replace the ANZ
$20 million Working Capital Facility.
4|P a g e
WHSP Facility Key Terms
Facility Limit
A$50 million
The Facility Limit can only be drawn down during the first 13
months of the Term (Availability Period)
Term
2 years with ability to extend for a further 1 year with consent of
the Lender
Repayment
The Facility is payable at the end of the Term but can be prepaid
at any time
Interest Rate
BBSY + 11% per annum (payable monthly)
PIK Interest
Interest may be capitalised monthly. Interest will accrue on such
capitalised amount at an additional 2% per annum
Security
Second ranking secured
Establishment Fee
3.5% of the Facility Limit
Exit Fee
3.5% of the Facility Limit if paid during the first 12 months
and 5 business days of the Term;
5% of the Facility Limit if paid after 12 months and 5
business days and before 18 months of the Term;
8.5% of the Facility Limit if paid after 18 months of the Term
Undrawn Commitment
Fee
5% per annum on the undrawn portion of the Facility Limit during
the Availability Period
Make Whole Fee
A make whole fee is payable if the whole or any part of the
Facility Limit is cancelled/repaid within the first 12 months
Conditions Precedent
Drawing of the first tranche is subject to conditions precedents
including:
delivery of executed finance documents for the transaction,
including a deed of priority between the Company, WHSP,
ANZ and Evolution Mining Limited;
payment in full the company’s existing working capital facility
with the ANZ;
Other usual lender requirements relating to the availability of
finance facilities and granting of security.
Subsequent tranches will be subject to no default or review
events occurring which are continuing
Covenants
Usual for a facility of this nature including with respect to:
Net Tangible Assets;
Debt to EBITDA; and
Interest cover ratio
5|P a g e
ASX Waiver
The granting of the second ranking security by the Company over its assets to secure
the Company’s obligations under the Facility (Relevant Security) is regarded as a
‘disposal’ of those assets by the Company to WHSP (as a 30%+ shareholder of the
Company, WHSP is considered a ‘person in a position of influence’ or a ’10.1 party’
under the Listing Rules). As the value of the assets the subject of the Relevant
Security exceeds 5% of the equity interests of the Company, the granting of the
Relevant Security requires shareholder approval under Listing Rule 10.1.
The Company has applied for a waiver from the requirement to obtain shareholder
approval under Listing Rule 10.1 and the ASX has granted a waiver on the terms set
out in Appendix 2.
In granting the waiver, ASX has considered Listing Rule 10.1 only and makes no
statement as to the Company’s compliance with other Listing Rules.
The Company has chosen to obtain the financial accommodation from WHSP (as
opposed to a third-party lender) having regard to the specific circumstances of the
Company. The Company’s current financier (ANZ) holds security over the
Company’s assets, and accordingly, any additional financier would only be able to
obtain security on a second ranking basis. This arrangement significantly limited the
terms of financing alternatives available to the Company (particularly as it relates
to new third-party financiers). On the other hand, WHSP, as a current substantial
shareholder in the Company, has a pre-existing and significant interest in, and
understanding of, the Company. Accordingly, when compared to a new thirdparty financier, the Company considered that WHSP was the best placed party to
be able to put forward a commercially acceptable financing package to the
Company that is secured by a second ranking security.
The Board also took steps to satisfy itself the transactions being entered into were on
arm’s length terms and were otherwise fair and reasonable from the perspective of
the Company’s shareholders, including:
consulting with an industry finance advisor; and
comparing the terms offered by WHSP against those announced recently by
other listed mining companies who have entered into similar style financing
arrangements (noting that a key feature of these other finance
arrangements is the inclusion of a requirement for a significant equity
component and the advantage to the Company’s shareholders with the
Facility is the absence of such a requirement).
The ANZ $20 million Working Capital Facility will be cancelled and a deed of priority
and subordination has been entered into between ANZ, WHSP, Evolution Mining
Limited and various Aeris group entities.
6|P a g e
Further information on Aeris’ activities is provided in the June Quarterly Activities
Report which was released on 31 July 2023.
This announcement is authorised for lodgement by:
Andre Labuschagne
Executive Chairman
ENDS
For further information, please contact:
Mr. Andre Labuschagne
Executive Chairman
Tel: +61 7 3034 6200, or visit our website at www.aerisresources.com.au
Media:
Ayla Djonlagic
Tel: 0402 763 968
ayla@sabio.com.au
About Aeris
Aeris Resources is a mid-tier base and precious metals producer. Its copper
dominant portfolio comprises four operating assets, a long-life development project
and a highly prospective exploration portfolio, spanning Queensland, Western
Australia, New South Wales and Victoria, with headquarters in Brisbane.
Aeris has a strong pipeline of organic growth projects, an aggressive exploration
program and continues to investigate strategic merger and acquisition
opportunities. The Company’s experienced board and management team bring
significant corporate and technical expertise to a lean operating model. Aeris is
committed to building strong partnerships with its key community, investment and
workforce stakeholders.
7|P a g e
APPENDIX 1 – OPERATIONAL GUIDANCE
FY24
Guidance
FY23A
kt
koz
koz
19 - 24
6-7
148 - 185
17.2
4.6
135
Operating Costs
Mining
Processing
Site G&A
TC/RCs
Product handling
$M
$M
$M
$M
$M
113 - 136
31 - 37
22 - 27
19 - 23
16 - 20
110
31
20
14
15
Capital Costs
Sustaining
Growth
Exploration
$M
$M
$M
57 - 69
10 - 12
7-9
46
39
6
FY24
Guidance
FY23A
Tritton Operations
Production
Copper
Gold
Silver
Cracow Operations
Production
Gold
koz
38 - 48
48.2
Operating Costs
Mining
Processing
Site G&A
$M
$M
$M
50 - 60
26 - 31
12 - 15
57
26
11
Capital Costs
Sustaining
Growth
Exploration
$M
$M
$M
18 - 22
23 - 28
4-5
11
4
5
8|P a g e
FY24
Guidance
FY23A
kt
kt
koz
koz
0.2 - 0.3
1.2 - 1.5
0.2 - 0.3
33 - 42
3.1
22.5
3.0
718
Operating Costs1
Mining
Processing
Site G&A
TC/RCs
Product handling
$M
$M
$M
$M
$M
5-6
3-4
2-3
2-3
1-2
48
28
31
19
17
Capital Costs
Sustaining
Growth
Exploration
$M
$M
$M
1-2
1-2
1-2
24
1
3
FY24
Guidance
FY23A
Jaguar Operations
Production
Copper
Zinc
Gold
Silver
North Queensland Operations
Production
Copper
Gold
kt
koz
8 - 10
4-5
7.1
3.9
Operating Costs
Mining
Processing
Site G&A
TC/RCs
Product handling
$M
$M
$M
$M
$M
34 - 41
25 - 30
7-8
7-9
7-9
44
20
7
7
4
Capital Costs
Sustaining
Growth
Exploration
$M
$M
$M
0-0
0-0
0-0
1
0
2
1 Excludes $7.2M closure and $4.5M care and maintenance costs
9|P a g e
APPENDIX 2 – ASX WAIVER
Based solely on the information provided, the ASX has granted the Company a waiver of
Listing Rule 10.1 to the extent necessary to permit the Company to grant security over the
assets of the Company in favour of WHSP to secure the Company’s obligations under the
Facility without obtaining shareholder approval, on the following conditions:
the material terms of the Facility and the waiver from Listing Rule 10.1 are
announced to the market;
the announcement includes a description of the reasons why the Company has
chosen to obtain the financial accommodation from the 10.1 party, rather than a
lender that is not a 10.1 party and the steps the board of the Company has taken
to satisfy itself that the acquisition is being entered into on arm’s length terms and is
fair and reasonable from the perspective of the holders of the Company’s ordinary
securities;
the security documents expressly provide that:
o
the security is limited to the funds due under the Facility;
o
the security will be discharged when the funds due under the Facility have
been repaid in full;
o
in the event the security is enforced, the assets can only be disposed of to
the 10.1 party or an associate of the 10.1 party if the disposal is first approved
by the Company’s security holders under Listing Rule 10.1; and
o
otherwise, if the holder of the security exercises, or appoints a receiver,
receiver and manager or analogous person to exercise any power of sale
under the security, the assets must be sold to an unrelated third party on arm’s
length commercial terms and the net proceeds of sale distributed to the 10.1
party in accordance with their legal entitlements;
any variation to the terms of the Facility or the security which:
o
advantages the 10.1 party in a material respect;
o
disadvantages the Company in a material respect; or
o
is inconsistent with the terms of the waiver,
must be subject to security holder approval under Listing Rule 10.1; and
for each year while they remain on foot, a summary of the material terms of the
financial accommodation and the security is included in the related party
disclosures in the Company’s audited annual accounts.
10 | P a g e
Share your feedback
Discover