QUARTERLY RESULTS PRESENTATION
Released
Released
Announcement PDF
Q2 FY26 Results
29 January 2026
Presented by: Andre Labuschagne
Disclaimer
This investor presentation has been prepared by Aeris Resources Limited
(“Aeris” or the “Company”). By attending an investor presentation or
briefing, or accepting, accessing or reviewing this presentation, you
acknowledge and agree to the terms set out below.
SUMMARY INFORMATION
This presentation is for information purposes only and should be read in
conjunction with the most recent financial reports and other documents
lodged by Aeris with the Australian Securities Exchange (“ASX”) in
connection with its continuous disclosure obligations. This presentation
does not purport to contain all of the information that an investor should
consider when making an investment decision nor does it contain all of
the information which would be required in a product disclosure
statement or prospectus prepared in accordance with the requirements
of the Corporations Act.
No reliance should be placed on the information or opinions contained
in this presentation, which are provided as at the date of this
presentation (unless otherwise stated) and to the maximum extent
permitted by law, Aeris has no obligation to update the information
contained in this presentation. An investment in securities is subject to
known and unknown risks, some of which are beyond the control of
Aeris. Investors should consult with their own legal, tax, business and/or
financial advisors in connection with any acquisition of securities.
FINANCIAL INFORMATION
All financial information set out in this presentation is expressed in
Australian Dollars unless stated otherwise. Investors should be aware that
certain financial measures included in this presentation are “non-IFRS
financial information” under ASIC Regulatory Guide 230: “Disclosing non-
IFRS financial information” published by ASIC and also “Non-GAAP
financial measures” within the meaning of Regulation G under the US
Securities Exchange Act of 1934 and are not recognised under the AAS
or IFRS. Aeris believes the non-IFRS financial information and non-GAAP
financial measures provide useful information to users in measuring the
financial performance and condition of Aeris.
However, investors should note that the non-IFRS financial information
and non-GAAP financial measures do not have standardised meanings
prescribed by AAS or IFRS. Therefore, the non-IFRS financial information is
not a measure of financial performance, liquidity or value under the IFRS
and may not be comparable to similarly titled measures presented by
other entities, nor should the information be construed as an alternative
to other financial measures determined in accordance with AAS or IFRS.
Investors are cautioned, therefore, not to place undue reliance on any
non-IFRS financial information included in this presentation.
FUTURE PERFORMANCE AND FORWARD-LOOKING STATEMENTS
This presentation contains certain ‘forward-looking’ statements, opinions
and estimates, which are based on assumptions and contingencies that
are subject to change without notice and involve known and unknown
risks and uncertainties beyond the control of Aeris and its officers. This
includes statements about market and industry trends, which are based
on interpretations of current market conditions.
Indications of, and guidance on, future earnings and financial position
and performance are forward-looking statements. As are statements
containing the words “expect”, “anticipate”, “estimate”, “intend”,
“believe”, “guidance”, “should”, “could”, “may”, “will”, “predict”, “plan”
and other similar expressions.
Forward-looking statements are based on information available to Aeris
as at the date of this presentation and should not be relied upon as an
indication or guarantee of future performance. Except as required by
law or regulation (including the ASX Listing Rules), none of Aeris, its
representatives or advisers undertakes any obligation to provide any
additional or updated information whether as a result of a change in
expectations or assumptions, new information, future events or results or
otherwise.
Investors are strongly cautioned against placing undue reliance on
forward-looking statements, especially considering the current economic
climate and significant volatility, uncertainty and disruption caused by
recent world events such as the COVID-19 pandemic and international
hostilities and associated economic changes.
DISCLAIMER
To the maximum extent permitted by law, Aeris and each of
its respective related bodies corporate, shareholders and affiliates, and
each of their respective officers, directors, partners, employees,
representatives, affiliates, agents, consultants and advisers (each a
“Limited Party”):
• expressly disclaim any and all responsibility and liability (including,
without limitation, any liability arising from fault, negligence or
negligent misstatement) for any direct, indirect, consequential or
contingent loss or damage arising from this presentation or reliance
on anything contained in or omitted from it or otherwise arising in
connection with this presentation;
• disclaim any obligations or undertaking to release any updates or
revisions to the information in this presentation and;
• do not make any representation or warranty, express or implied, as to
the accuracy, reliability, completeness or fairness of the information,
opinions and conclusions contained in this presentation or that this
presentation contains all material information about Aeris or the
Transaction or that a prospective investor or purchaser may require in
evaluating a possible investment in Aeris or acquisition of shares in
Aeris, or likelihood of fulfilment of any forward-looking statement or
any event or results expressed or implied in any forward-looking
statement.
2
Disclaimer
NO NEW INFORMATION STATEMENT
This presentation refers to Exploration Results, estimates of Mineral
Resources and Ore Reserves contained in the Group Mineral Resource
and Ore Reserve Statement as at 31 December 2024 (announced on 22
July 2025 “Group Mineral Resource and Ore Reserve Statement”), as well
as an Ore Reserve Estimate for Constellation (announced on 28 October
2025, “Maiden Open Pit Ore Reserve Estimate for Constellation Project”)
and prior market announcements released by Aeris, (Prior Reports). The
Prior Reports are footnote referenced in this presentation and available
from: https://www.aerisresources.com.au/investor.
Aeris confirms that it is not aware of any new information or data that
materially affects the information included in the Prior Reports and, in the
case of Exploration Results, estimates of Mineral Resources or Ore
Reserves, that all material assumptions and technical parameters
underpinning the results or estimates in the Prior Reports continue to
apply and have not materially changed. Aeris confirms that the form
and context in which the Competent Person’s findings are presented in
this document have not been materially modified from the Prior Reports.
NOT FOR DISTRIBUTION OR RELEASE IN THE UNITED STATES
This Presentation does not constitute an offer to sell, or the solicitation of
an offer to buy, any securities in the United States. The securities referred
to in this Presentation have not been, and will not be, registered under
the US Securities Act of 1933 (the "US Securities Act") or the securities laws
of any state or other jurisdiction of the United States, and may not be
offered or sold, directly or indirectly, to any person in the United States or
to any person acting for the account or benefit of a person in the United
States unless they have been registered under the US Securities Act
(which Aeris has no obligation to do or to procure) or are offered or sold
pursuant to an exemption from, or in a transaction not subject to, the
registration requirements of the US Securities Act and any applicable
securities laws of any state or other jurisdiction of the United States.
3
Australian mid-tier, base and precious metals producer
Aeris Resources
2 producing operations (FY26: 40-49kt copper eq.)1
3 development projects
Investing in exploration
Substantial copper production and metal inventory
Excellent platform for growth
4
1. Cu Eq t = ((Cu Produced x Cu $/t) + (Au Produced x Au $/oz) + (Ag Produced x Ag $/oz)) / (Cu $/t)
Assumed average commodity prices FY26: US$9,429/t Cu, US$3,241/oz Au, US$35/oz Ag. Aeris confirms that it is the
Company’s opinion that all the elements included in the metal equivalents calculation have a reasonable potential to
be recovered and sold.
5
Aeris strategy for FY26
5
Realise
value for
shareholders
01
Sell non-core assets
02 Divesting North Queensland
exploration assets for total
consideration up to $15.5M1
• Completion Q3 FY26
Operational Delivery
Tritton
• Murrawombie Pit
• Constellation on time
• Resource extension
• LOM
Cracow
• Golden Plateau
• Resource extension
• LOM
05
Growth
• Focus on life extensions
through greenfield exploration
• Consider external
opportunities
Balance Sheet
06
Repay debt by August 26
Assets sales
Consider hedging strategy
Unlock Stockman
04
Finalise Albion test work
• Update feasibility study
• Concept study on acid
production
03 Jaguar strategy
Focus on +10 year life
• Reduce care and maintenance
• Test base metals targets
1. Refer to ASX release “Agreement to Divest North Queensland Copper Assets”, 27 October 2025
6
Key points for Q2 FY26
6
Group copper equivalent production of 10.1kt1
Costs well managed across the group
Cash and receivables at end of quarter up to $106.4M
Successful completion of $80M placement and $21.6M SPP
WHSP loan facility repaid – Aeris now debt free
Tritton production of 5.0kt Cu at AISC of A$3.94/lb, lower quarter on
quarter but in line with plan as Murrawombie Pit focused on waste
stripping
High grade intersections from drilling testing resource extensions at
Avoca Tank and Budgerygar (Tritton)
Cracow gold production of 11.1koz at AISC of A$3,278/oz, ahead of
plan
Drilling commenced at Golden Plateau open pit target (Cracow)
Divestment of North Queensland due to complete next quarter
Solid operating performance and strong closing cash position
1. Refer to ASX release September 2025 Quarterly Activities Report for production detail.
CuEq = ((Cu Produced x Cu $/t) + (Au Produced x Au $/oz) + (Ag Produced x Ag $/oz)) / (Cu $/t)
Q2 prices US$11,100/t Cu, US$4,146/oz Au, US$55/oz Ag
7
7
Quarter Cash Flow
Dec Quarter Group Cash Flow ($M)
Stronger cash balance after equity raise and debt repayment
1 - OCF = operating cash flow
2 - Proceeds from Equity Riase are net of direct costs
3 - Finance and other includes gold hedging
8
8
YTD Cash Flow
YTD Group Cash Flow ($M)
1 - OCF = operating cash flow
2 - Proceeds from Equity Riase are net of direct costs
3 - Finance and other includes gold hedging
Tritton
NSW
Production lower Q on Q, as planned
Q2 FY26 results
Production of 5.0kt Cu at AISC of A$3.94/lb
Tonnes milled lower Q on Q due to Stage 1 pit ore stockpile
processed in Q1 and 10 day mill shutdown in Q2
Costs well managed and to plan
Third-party concentrate railing impacted by fire on rail bridge
Over 13,000m of diamond drilling completed with 4 rigs
Constellation development consent received
High-grade intersections returned from drilling testing resource
extensions at Avoca Tank and Budgerygar
10
FY26
Guidance
YTD
Dec 25
Qtr
Sep 25
Qtr
Unit
Production Summary
529.8
245.1
284.7
kt
Ore Mined
2.06
2.16
1.98
% Cu
Mined Grade
610.0
251.8
358.3
kt
Ore Milled
1.9
2.1
1.8
% Cu
Milled Grade
95.3
95.7
95.0
% Cu
Recovery
24 – 29
11.1
5.0
6.1
kt
Copper Produced
8 – 10
3.8
1.8
2.0
koz
Gold Produced
215 – 263
108.8
36.6
72.2
koz
Silver Produced
Cost Summary
55.2
27.2
28.0
A$M
Mining
17.2
8.6
8.6
A$M
Processing
12.4
6.3
6.1
A$M
Site G&A
2.7
1.2
1.5
A$M
TC/RCs
8.8
3.5
5.3
A$M
Product Handling
207 – 253
96.3
46.8
49.5
A$M
Total Mine Operations
(27.9)
(13.2)
(14.8)
A$M
By-Product Credit
6.6
3.0
3.6
A$M
Royalties
1.1
0.5
0.5
A$M
Corporate G&A
(2.7)
(6.8)
4.0
A$M
Inventory Movements
39 – 48
27.5
13.2
14.3
A$M
Sustaining Capital
100.8
43.6
57.3
A$M
All-In Sustaining Costs
4.11
3.94
4.24
A$/lb
58 – 71
49.0
23.3
25.6
A$M
Growth Capital
10 – 12
2.5
0.7
1.8
A$M
Exploration
152.3
67.6
84.7
A$M
All-In Costs
6.20
6.12
6.27
A$/lb
Stage 2 cutback
Murrawombie Pit
Stage 2 waste stripping underway – no ore
mining during the quarter
Minor pit redesign for geotechnical risk
management
Updated grade control model shows 10%
increase in contained metal
Stage 2 ore to be delivered to the mill next
quarter
11
New mineralisation along strike from Avoca Tank
Tritton exploration
Two drill holes intersected high grade copper 50-100m south of
Avoca Tank resource
ATEL128 22.2m1 @ 3.23% Cu, 0.08g/t Au, 3.8g/t Ag (from
296.8m)
ATEL127 9.4m1 @ 1.65% Cu, 0.63g/t Au, 8.0g/t Ag (from
253.3m)
13 hole program underway
Two further holes completed awaiting assays
12
1. Estimated true thickness is between 35% to 100% of the reported thickness interval. Refer to ASX release
Clarification - Tritton Operation Drilling Update, dated 18 Dec 2025.
Thicker drill intersections from Budgerygar
Tritton exploration
Drilling targeting Inferred Mineral Resource and potential
extensions below the base of the know resource
Has returned significantly thicker copper intersections than
expected
BDEL089 24.0m1 @ 1.76% Cu, 0.03g/t Au, 3.1g/t Ag (from
108.0m)
BDGC155 22.8m1 @ 2.40% Cu, 0.10g/t Au, 5.3g/t Ag (from
93.0m)
BDGC156 21.7m1 @ 1.80% Cu, 0.03g/t Au, 2.8g/t Ag (from
88.65m)
BDGC135 16.6m1 @ 1.52% Cu, 0.04g/t Au, 3.1g/t Ag (from
107.2m)
Drilling continuing with two rigs
13
1. Estimated true thickness is between 50% to 100% of the reported thickness interval. Refer to ASX release
Clarification - Tritton Operation Drilling Update, dated 18 Dec 2025.
Cracow
Queensland
Q2 FY26 results
Gold production 11.1koz, ahead of plan, at AISC of
A$3,278/oz
Costs well managed and on plan
TSF lift completed ahead of schedule
Drilling commenced at Golden Plateau pit target
15
Quarter production ahead of plan, costs on track
FY26
Guidance
YTD
Dec 25
Qtr
Sep 25
Qtr
Unit
Production Summary
293.2
150.9
142.3
kt
Ore Mined
2.33
2.49
2.16
g/t
Mined Grade
311.6
157.3
154.3
kt
Ore Milled
2.21
2.43
1.98
g/t
Milled Grade
90.4%
90.5%
90.4%
Au
Recovery
36 – 46
20.0
11.1
8.9
koz
Gold Produced
19.8
11.0
8.8
koz
Gold Sold
Cost Summary
35.8
16.2
19.6
A$M
Mining
14.3
7.1
7.2
A$M
Processing
5.7
2.9
2.8
A$M
Site G&A
95 – 116
55.8
26.3
29.6
A$M
Total Mine Operations
(1.0)
(0.5)
(0.5)
A$M
By-Product Credit
6.3
3.7
2.6
A$M
Royalties
0.8
0.4
0.4
A$M
Corporate G&A
(1.0)
0.9
(1.9)
A$M
Inventory Movements
18 – 22
7.7
5.4
2.3
A$M
Sustaining Capital
68.6
36.1
32.5
A$M
All-In Sustaining Costs
3,461
3,278
3,692
A$/oz
6 – 8
7.6
2.1
5.5
A$M
Growth Capital
5 – 7
1.7
0.7
1.0
A$M
Exploration
77.9
38.9
39.0
A$M
All-In Costs
3,931
3,528
4,437
A$/oz
Cracow exploration
16
Drilling at Golden Plateau
Drill program commenced to test remnant mineralisation
around historic stoping areas
7,000m drill program underway
Second drill rig mobilised in early January
Golden Plateau is a key target for resource growth and mine
life extension at Cracow
Projects
Q2 FY26 activities
Jaguar – on care and maintenance
Jaguar – base metal exploration program to commence next
quarter
Stockman – reviewing next steps to progress project
North Queensland – divestment expected to be completed next
quarter
18
Project updates
19
Corporate
Closing cash and receivables increased to $106.4 million
Restricted cash related to environmental bonds unchanged at ~$17
million
Cash flow from operations of $44 million impacted by ~$18 million due
to rail disruptions preventing concentrate stockpiles to be invoiced
Successful completed $80 million placement and $21.6 million
oversubscribed SPP
$40 million drawn WHSP facility repaid and cancelled – Aeris now
debt free
Dec
Sep
(A$ Million) 2025
2025
QTR
QTR
87.9
32.0
Closing cash
18.4
14.4
Tritton - Copper concentrate receivables
106.4
46.4
Useable Cash and Receivables
Dec
Sep
(A$ Million) 2025
2025
QTR
QTR
32.0
28.2
Opening cash
44.0
53.1
Cash flow from operations
(43.8)
(46.6)
Cash flow from capital expenditure
55.8
(2.7)
Cash flow from financing
87.9
32.0
Closing cash
Australian mid-tier, base and precious metals producer
Aeris Resources
2 producing operations (FY26: 40-49kt copper eq.)1
3 development projects
Investing in exploration
Substantial copper production and metal inventory
Excellent platform for growth
20
1. Cu Eq t = ((Cu Produced x Cu $/t) + (Au Produced x Au $/oz) + (Ag Produced x Ag $/oz)) / (Cu $/t)
Assumed average commodity prices FY26: US$9,429/t Cu, US$3,241/oz Au, US$35/oz Ag. Aeris confirms that it is the
Company’s opinion that all the elements included in the metal equivalents calculation have a reasonable potential to
be recovered and sold.
Thank You
Appendix
Group Ore Reserves
23
As at December 2024. Refer to ASX announcement “Group Mineral Resource and Ore Reserve Statement” dated 22 July 2025
Contained Metal
Grade
Tonnes
(‘000)
Category
BASE METALS
Ag (koz)
Au (koz)
Zn (kt)
Cu (kt)
Ag (g/t)
Au (g/t)
Zn (%)
Cu (%)
Asset
-
-
-
1
-
-
-
0.7
100
Proved
Tritton
444
23
-
36
6
0.3
-
1.6
2,280
Probable
444
23
-
37
6
0.3
-
1.5
2,380
Total
-
-
-
-
--
-
--
-
-
Proved
North Qld
-
9
-
30
-
0.2
-
1.9
1,600
Probable
-
9
-
30
-
0.2
-
1.9
1,600
Total
-
-
-
-
-
-
-
-
-
Proved
Stockman
11,409
318
413
183
37
1.0
4.3
1.9
9,640
Probable
11,409
318
413
183
37
1.0
4.3
1.9
9,640
Total
-
-
-
1
-
-
-
0.7
100
Total Proved
Total
11,853
350
413
249
27
0.8
3.1
1.8
13,530
Total Probable
11,853
350
413
249
27
0.8
3.0
1.8
13,630
Grand Total
Contained Metal
Grade
Tonnes (‘000)
Category
GOLD
Ag (koz)
Au (koz)
Zn (kt)
Cu (kt)
Ag (g/t)
Au (g/t)
Zn (%)
Cu (%)
Asset
-
14
-
-
-
3.0
-
-
145
Proved
Cracow
-
33
-
-
-
2.9
-
-
360
Probable
-
48
-
-
-
2.9
-
-
505
Grand Total
Total
Group Mineral Resources
24
Contained Metal
Grade
Tonnes
(Mt)
Category
BASE METALS
Ag (koz)
Au (koz)
Zn (kt)
Cu (kt)
Ag (g/t)
Au (g/t)
Zn (%)
Cu (%)
Project
30
1
-
4
2
0.1
-
1.0
0.4
Measured
Tritton
1,270
158
-
179
4
0.4
-
1.6
11.0
Indicated
840
73
-
131
4
0.3
-
1.8
7.5
Inferred
2,140
233
-
314
4
0.4
-
1.7
18.9
Total
1,030
4
25
8
63
0.3
5.0
1.6
0.5
Measured
Jaguar
8,950
53
268
59
67
0.4
6.4
1.4
4.2
Indicated
5,260
62
128
23
83
1.0
6.5
1.1
2.0
Inferred
15,240
119
422
90
71
0.6
6.3
1.4
6.6
Total
0
3
-
5
0
0.5
-
2.3
0.2
Measured
North Qld
210
16
-
47
3
0.2
-
2.0
2.4
Indicated
30
2
-
12
2
0.1
-
2.0
0.6
Inferred
240
21
-
64
2
0.2
-
2.0
3.2
Total
0
-
-
-
0
-
-
-
-
Measured
Stockman
16,000
420
561
288
37
1.0
4.2
2.1
13.4
Indicated
2,440
117
62
27
32
1.5
2.6
1.1
2.4
Inferred
18,450
537
624
315
36
1.1
4.0
2.0
15.8
Total
1,060
9
25
17
29
0.2
2.3
1.5
1.1
Total Measured
Total
26,440
647
829
574
27
0.6
2.7
1.9
31.0
Total Indicated
8,580
254
191
193
22
0.6
1.5
1.6
12.4
Total Inferred
36,070
910
1,045
784
25
0.6
2.3
1.8
44.5
Grand Total
Contained Metal
Grade
Tonnes
(Mt)
Category
GOLD
Ag (koz)
Au (koz)
Ag (g/t)
Au (g/t)
Asset
37
46
3
4.0
0.4
Measured
Cracow
229
224
4
3.6
1.9
Indicated
305
181
4
2.6
2.1
Inferred
571
452
4
3.2
4.4
Grand Total
Total
As at December 2024. Refer to ASX announcement “Group Mineral Resource and Ore Reserve Statement” dated 22 July 2025
25
25
1. Cu Eq t = ((Cu Produced x Cu $/t) + (Au Produced x Au $/oz) + (Ag Produced x Ag $/oz)) / (Cu $/t)
Assumed average commodity prices FY26: US$9,429/t Cu, US$3,241/oz Au, US$35/oz Ag. FY25 as detailed in
quarterly reports. Aeris confirms that it is the Company’s opinion that all the elements included in the metal
equivalents calculation have a reasonable potential to be recovered and sold.
2. Excludes royalties
3. FY25 results unaudited
FY26 Guidance
FY25 Actual
FY26 Guidance
Group
Production
24.9
24 - 29
kt
Copper
55.2
44 - 56
koz
Gold
185.2
240 - 293
koz
Silver
42.1
40 - 49
kt
Copper equivalent1
Operating Costs
344.9
302 - 369
$M
Mine operations2
10.8
6 - 7
$M
Care and maintenance
23.6
21 - 26
$M
Corporate
Capital Costs
69.4
57 - 70
$M
Sustaining
35.1
65 - 80
$M
Growth & projects
9.8
18 - 23
$M
Exploration
FY25 Actual
FY26 Guidance
Tritton
Production
19.4
24 - 29
kt
Copper
6.1
8 - 10
koz
Gold
185.2
215 - 263
koz
Silver
Operating Costs
202.1
207 - 253
$M
Mine operations
Capital Costs
52.5
39 - 48
$M
Sustaining
32.0
58 - 71
$M
Growth
2.9
10 - 12
$M
Exploration
FY25 Actual
FY26 Guidance
Cracow
Production
45.1
36 - 46
koz
Gold
Operating Costs
99.4
95 - 116
$M
Mine operations
Capital Costs
16.7
18 - 22
$M
Sustaining
0.0
6 - 8
$M
Growth
5.3
5 - 7
$M
Exploration
Share your feedback