ANNUAL REPORT 30 JUNE 2024
Released
Released
Announcement PDF
Aeris Resources
Annual Report
2024 Highlights
Operations
3
1
2
Operating assets
Operation in Care
and Maintenance
Advanced
development projects
Safety 1.2 LTIFR
down from 1.7 in FY23
Diversity
16%
Female participation rate
11%
Aboriginal and Torres Strait
Islander participation rate
Production
Financial
Net Assets
$271.8m
19.7kt Copper
up from $266.4m in FY23
up from 17.2kt in FY23
Tritton Copper Operations
Adjusted EBITDA1
$107.0m
up from $32.0m in FY23
45.7koz Gold
down from 48.2koz in FY23
Cracow Gold Operations
1. Refer to Adjusted EBITDA reconciliation on page 79
Net Cash from
operating activities
$62.5m
up from $59.3m in FY23
We are Aeris Resources
Aeris Resources is a mid-tier base and precious metals
producer. Our copper-dominant portfolio comprises
of three operating assets, a mine on care and
maintenance, two advanced development projects
and a highly prospective exploration portfolio.
Contents
EXECUTIVE CHAIRMAN’S LETTER
2
RESOURCES AND RESERVES
22
REVIEW OF OPERATIONS
3
SUSTAINABILITY REPORT
26
DIRECTORS’ REPORT
69
Operating Review
73
Financial Review
78
Financial Results
4
Financial Position
4
Tritton Operations
6
Cracow Operations
10
North Queensland Operations
14
Jaguar Operations
16
Stockman Project
20
Letter from the Remuneration Committee
Chairman86
Shareholder Information
153
Glossary154
Corporate directory
155
EXECUTIVE CHAIRMAN’S
LETTER
The 2024 financial year was a pleasing improvement on the previous year.
Importantly, we delivered on what we said we would do, achieving group level
production and costs in line with market guidance. We also advanced study
work on key growth projects and continued exploration activities to extend the
lives of our mines.
Tritton had a much-improved FY24 producing almost 20kt copper and achieving guidance. The investment
into new mine developments at Avoca Tank and Budgerygar last year has started paying off with both
mines delivering increased production tonnages at significantly higher grades. Exploration activities at
Tritton focused on the Constellation deposit, which has the potential to be a long-life ore source for the
operation in the future.
At Cracow, we invested $17.3 million on a tailings dam lift to provide a further three years of production
capacity. Operationally Cracow performed well, comfortably meeting planned production and cost
targets. Exploration is focused on near mine targets in the Western Vein Field to extend the life of the
operation.
In North Queensland, the Mt Colin mine continued to perform well although challenges in securing
toll processing slots at Ernest Henry resulted in lower than planned copper production for the year.
Through improved mining practices and mine design, we were also able to extend the life of Mt Colin
approximately a further six months into mid-FY25. Focus for the North Queensland Operations in FY25 will
now turn to finalisation of the feasibility study and permitting work on the Barbara copper project.
Production at Jaguar was completed at the end of the first quarter of FY24 and the operation transitioned
to care and maintenance. We were proud of the way the team at Jaguar worked to maximise the final
production from the mine while transitioning the operation in a safe and controlled manner into care and
maintenance. We are currently undertaking studies on options to restart Jaguar and will provide further
information in FY25. We are also excited by the exploration potential at Jaguar and have initiated an
exploration program focused on the gold potential on the tenements.
Significant progress was made on the Stockman project, with a long-life mine design completed, and a
new processing flowsheet being investigated to provide a step change in metal recovery.
I am also pleased to report that our focus on workplace safety through employee training and hazard
identification has seen a significant decrease in work-related injuries. Our people are the key to our
success, and I thank them for their dedication again this year.
On the sustainability front, we have adopted new standards for assessing and reporting key activities.
We are committed to enhancing our sustainability practices, with our overarching philosophy of “good for
business, good for others” guiding our efforts.
Our performance in FY24 was greatly improved across the business and we look forward to continuing to
build on this success in the coming years and to deliver value to our shareholders.
Andre Labuschagne
Executive Chairman
2
|
AERIS RESOURCES
Review of
Operations
Aeris has three operating assets,
Tritton Operations, Cracow
Operations, and North Queensland
Operations. Jaguar Operations is
in care and maintenance, and the
Stockman Project and the Barbara
Project are development projects.
2024 ANNUAL REPORT
|
3
FINANCIAL RESULTS
During the year ended 30 June 2024, the consolidated entity recorded an Adjusted EBITDA1 of
$107.039 million, $75.025 million higher than the previous year (2023: $32.014 million). Similarly,
the consolidated entity’s loss after tax of $24.258 million, presented a strong improvement from a
loss after tax of $139.754 million, for the year ended 30 June 2023.
Revenue from contracts with
• Revenue from North Queensland
Care and maintenance costs of
customers was $540.020 million,
Operations of $96.991 million was
$7.857 million, for Jaguar operations,
compared to $612.490 million for the
lower than prior corresponding
were recognised for FY24 along
previous corresponding period. This
period ($107.698 million) due to
with employee separation costs
reflects the following factors:
timing of third party processing
amounting to $5.824 million.
• Tritton revenue of $272.603
million was higher than the prior
corresponding period ($208.659
runs, offset partially by improved
copper prices realised;
• Jaguar Operations contributed
million) due to higher copper
$23.379 million in revenue
production (19,749 tonnes vs 17,205
(compared to $166.007 million for
tonnes in FY23) and higher copper
the previous corresponding period)
price received (A$13,365/t vs
prior to being put on care and
A$11,045/t);
maintenance in September 2023.
• Cracow revenue of $147.026 million
compared to $130.120 million in
FY2023, due to higher gold prices
(A$3,174/oz vs A$2,698/oz), partially
offset by lower gold produced
(45,651oz vs 48,221oz);
Cost of goods sold decreased to
$504.353 million from $705.464
A foreign exchange loss of $1.081
million was recognised for the year
ended 30 June 2024 (30 June 2023:
gain of $1.969 million).
Finance costs of $21.505 million were
significantly higher when compared
to $8.511 million in the prior
corresponding period, primarily due
to the interest charges on the WHSP
Debt Facility.
million in the prior corresponding
period largely due to Jaguar being
placed in care and maintenance in
September 2023.
FINANCIAL POSITION
At 30 June 2024, the consolidated entity had a positive net asset position of $271.788 million
(30 June 2023: $266.369 million).
The June 2024 net asset position
• In November 2023, the Company
• Working capital deficit of $33.354
for the consolidated entity was
undertook a $30.0 million fully
million, compared to a working
impacted by a number of key factors,
underwritten equity raise, to
capital deficit in the prior year of
including:
provide general working capital
$55.501 million, as creditors from
and increased financial flexibility;
FY23 were paid down in FY24 using
• On 2 August the Company
announced that it had entered into
• Investments of $30.358 million into
a $50 million WHSP Debt Facility
new mining projects, including
(as at 30 June 2024 $40 million was
exploration for the financial year
drawn);
ended 30 June 2024, compared to
$59.784 million in the corresponding
period; and
1. Refer to Adjusted EBITDA reconciliation on page 79
4
|
AERIS RESOURCES
debt and equity funds raised.
2024 ANNUAL REPORT
|
5
TRITTON OPERATIONS
HIGHLIGHTS
OPERATIONS
19.7kt of copper produced
at AISC of A$5.51/lb
Tritton Operations produced 19.7kt of copper in FY24, meeting
annual production guidance. Costs were well controlled for the year
with all capital and operating costs at the lower end of the published
guidance range.
Ramped up production from
high-grade Avoca Tank and
Budgerygar mines
Jameson Cell installed at
processing plant, resulting
increased copper content
in concentrate
During FY24, production levels
At the processing plant, the Jameson
ramped up at the new Avoca Tank
Cell was successfully commissioned
and Budgerygar mines. The higher
resulting in improved concentrate
grades in these mines contributed
grades. Metallurgical recovery was
to the significant increase in mined
slightly above plan for the year,
grade and produced copper
averaging 95.0%.
from the previous financial year.
Operational issues with equipment
and labour availability were
addressed with additional trucks
Updated Mineral Resource
Estimate for Avoca Tank
and loaders and contractor labour.
Limited growth capital was incurred
at Tritton for the year with the Avoca
Tank and Budgerygar mines now in
production.
Production at Murrawombie was
prioritised in the later half of the year
to ensure underground mining would
be completed ahead of the open pit
cutback commencing in FY25.
Units
FY24
FY23
FY22
1,195,375
1,369,364
1,488,120
1.69
1.36
1.30
1,215,692
1,352,424
1,500,463
Ore mined
tonnes
Grade mined
% Cu
Ore milled
tonnes
Grade milled
% Cu
1.71
1.34
1.30
Recovery
%
95.0
94.6
94.6
Total copper
tonnes
19,749
17,205
18,581
Oz
4,899
4,582
4,312
produced
Gold produced
6
| AERIS RESOURCES
EXPLORATION
In FY24, the Mineral Resource Estimate (MRE) for Avoca Tank was updated with new drilling information2.
The updated MRE resulted in a 35% increase in copper grade and 16% increase in contained copper metal.
The MRE is shown in the table below. The Avoca Tank mineralised system remains open down-plunge. Mineralisation has
been traced 340m down-plunge, and there remains significant potential to increase the MRE with further drilling.
Resource
Category
Cut-off
grade
(Cu%)
Tonnage
(kt)
Cu (%)
Au (g/t)
Ag (g/t)
Cu metal
(kt)
Au metal
(koz)
Ag metal
(koz)
-
-
-
-
-
-
-
420
3.3
1.0
16
14
13
211
Inferred
300
3.5
1.2
17
11
11
171
Total
720
3.4
1.1
17
24
24
382
Measured
Indicated
0.6
Notes:
1. The table above reflects the ASX announcement “Avoca Tank Mineral Resource Update” dated 25th October 2023
2. A
ngela Dimond MAusIMM takes Competent Person responsibility for this Mineral Resource Estimate in accordance with the JORC Code
(2012).
3. The underground cut-off of 0.6% Cu is currently used for life-of-mine planning at most deposits at the Tritton Operation.
4. T he Competent Person considers that the Mineral Resource has reasonable prospects for eventual economic extraction at the
reported cut-off grade.
5. Numbers may not sum due to rounding.
Two drill programs were also undertaken at the Constellation deposit. The first program targeted the deeper primary
sulphide portion of the deposit below the MRE. Five of the six holes intersected copper mineralisation, successfully
extending the known sulphide mineralisation 100m along strike and 200m down-plunge of the current MRE. Drill hole
TAKD095 returned the most significant intersection from the primary sulphide domain to date outside the current MRE:
25.95m at 3.81% Cu, 1.12g/t Au, 10.3g/t Ag (from 460m)3
2. Refer to ASX announcement “Avoca Tank Mineral Resource Update” dated 25th October 2023
3. R
efer to ASX announcement “High-grade copper intersected at Constellation” dated 20 th September 2023
2024 ANNUAL REPORT
|
7
Long section looking west showing the August 2022 Constellation Mineral Resource and the base of drilling
from the 2024 resource definition drill program4
The second drill program focused on the interpreted subvertical mineralised zone on the northern margin of the deposit
(referred to as the “stand-up zone”) and on improving resource confidence. At the end of the year, seven holes had
been completed with drilling continuing through the first half of FY25 5.
4. R
efer to ASX releases “High-grade copper intersected at Constellation” dated 20 September 2023 and “Constellation drilling update”
dated 7 November 2023
5. Refer to ASX announcement “Quarterly activities report – June 2024” dated 30 th July 2024
8
|
AERIS RESOURCES
2024 ANNUAL REPORT
|
9
CRACOW OPERATIONS
HIGHLIGHTS
OPERATIONS
45.7koz gold produced
at AISC of A$2,496/oz
Cracow Operations produced 45.7koz gold in FY24, towards the upper
end of production guidance. All operating and capital costs for the year
were at the low end of guidance ranges.
Tailings storage facility
upgrade provides Cracow
an additional 1 million cubic
metres of capacity to extend
the mine life
Cracow Operations performed well
During the year, the tailings storage
for the year, achieving planned
facility upgrade was completed at a
production. Mining operations
cost of $17.3 million. The project was
continued in the Western Vein Field.
completed ahead of schedule and
Grades and metallurgical recoveries
below budget and provides Cracow
in FY24 were higher year on year.
an additional 1 million cubic metres
of tailings capacity to extend the
mine life.
Drill program reported
high-grade gold mineralisation
from the Apollo structure
15-hole exploration program
completed at the Golden
Plateau deposit
Completed tailings storage facility
10
| AERIS RESOURCES
UNITS
FY2024
FY2023
FY2022
Ore Mined
kt
451.0
575.4
505.3
Mined Grade
g/t Au
3.13
2.75
3.26
Ore Milled
kt
585.3
667.0
663.9
Milled Grade
g/t Au
2.65
2.50
2.80
Recovery
%
91.6
90.0
90.2
Gold Produced
koz
45.7
48.2
53.9
EXPLORATION
Exploration activities at Cracow focused on
near mine extensions to mineralisation in
the Western Vein Field.
Five priority targets were drill tested with all targets
returning anomalous gold mineralisation. Within the
second half of the reporting period follow-up drilling
commenced, targeting the Apollo, Bazsickle and
Coronation West targets. High-grade gold mineralisation
was reported from the Apollo structure6.
Plan view of the Cracow Western Vein Field showing key exploration targets
6. Refer to ASX announcement “Quarterly Activities Report – March 2024” dated 30 th April 2024
2024 ANNUAL REPORT
|
11
Oblique view looking northwest showing drill hole pierce points through the Apollo structure at the
Western Vein Field.
A’
A
1600mRL
Geology
Structure (unaltered)
Structure (altered)
Breccia
KLU287
KLU287W1
Breccia Lode
Quartz Lode
Cross cutting structure
1500mRL
Drill hole assay results (Au g/t)
Previously
Reported
KLU164
KLU280
1400mRL
KLU213
KLU283
KLU285
KLU279
1300mRL
KLU212A
KLU284A
KLU282
KLU281
New
Results
<1.5
1.5 - 2.2
2.2 – 3.5
3.5 – 4.5
4.5 – 6.0
6.0 – 10
>10
Assays pending
No significant intersection
Cracow Operation
Apollo Structure
Oblique View – Looking northwest
0
50
100m
KLU286
1200mRL
A 15-hole exploration program was
Previous drill programs completed by
Several holes targeted strike
also completed at the Golden Plateau
Aeris to inform the maiden Mineral
extensions to the modelled Chaz
deposit in the Eastern Vein Field. The
Resource Estimate were focused on
and King lodes. Drilling intersected
program was focused on testing gold
the Harry’s, Chaz and King north-
epithermal quartz veining with
prospectivity along the remaining
south structures only. Although drilling
modest drill grades7. An updated MRE
untested interpreted structures south
successfully intersected the structures,
for Golden Plateau is expected to be
of the historical workings.
they failed to host epithermal quartz
completed in early FY25.
veining/gold mineralisation. The
prospectivity along these structures
has been downgraded.
7. Refer to ASX announcement “Quarterly Activities Report – June 2024” dated 30 th July 2024
12
|
AERIS RESOURCES
2024 ANNUAL REPORT
|
13
NORTH QUEENSLAND OPERATIONS
HIGHLIGHTS
OPERATIONS
6.8kt of copper produced
at AISC of A$4.64/lb
6.8kt of copper was produced in FY24 from the Mt Colin mine at
North Queensland Operations. Mining operations performed better
than plan for the year however, the lack of toll processing windows
resulted in copper production below the guidance range. Costs were
within guidance.
Lack of toll processing slots
resulted in copper production
below guidance
During FY24, mining at Mt Colin
was focused on final stopes, the
cave zone below the old open pit
Mined ore stockpiles onsite
ready for processing
and on pillar extraction. The cave
zone performed well and mining
tonnages were above plan. The
ability to continue to draw the cave
Mt Colin mine life extended
into mid-FY25
Feasibility Study for the Barbara
Project commenced
Queensland during the year.
BARBARA PROJECT
with additional pillar recovery, has
underground copper mine to be
enabled the mine life of Mt Colin to
developed beneath the old Barbara
be extended into mid-FY25.
open pit, which ceased operations
A lack of available toll processing
slots at Ernest Henry however resulted
production for the year was below
guidance. Metallurgical recoveries
were also negatively impacted by
the increased volumes of oxidised
and transitional ore through the
processing plant. At the end of
the year, significant stockpiles of
mined ore remained at the mine
site and Ernest Henry, available for
later processing.
AERIS RESOURCES
were undertaken in North
The Barbara Project is a potential
a result, total copper and gold
|
No material exploration activities
material longer than expected along
in reduced milled tonnages. As
14
EXPLORATION
in 2020. A feasibility study on the
project has commenced and is due
for completion in early FY25. Aeris
has also submitted the Environmental
Amendment for the proposed
underground mining operations
and is currently in discussions with
the regulator regarding the
permitting pathway.
UNITS
FY2024
FY2023
Ore Mined
kt
510.5
426.1
Mined Grade
% Cu
2.15
2.39
Ore Milled
kt
410.9
362.9
Milled Grade
% Cu
2.11
2.18
Recovery
% Cu
78.3
89.8
Copper Produced
kt
6.8
7.1
Gold Produced
koz
4.3
3.9
2024 ANNUAL REPORT
|
15
JAGUAR OPERATIONS
HIGHLIGHTS
OPERATIONS
Final mining and processing
completed and transitioned
to care and maintenance
Jaguar Operations completed final mining and processing in
September 2023 and transitioned to care and maintenance.
Jaguar Operations had a strong final quarter of production with mining
tonnages and metal production ahead of guidance. A team of 11 people
Prefeasibility study for restart
options commenced
manage care and maintenance and exploration activities for Jaguar
Operations. Aeris has commenced a prefeasibility study on a restart of Jaguar
Operations. The study is investigating mining scenarios from the four known
deposits (Bentley, Jaguar, Teutonic Bore and Triumph) along with options to
Updated Mineral Resource
Estimate completed
increase mill throughput and improve metal recovery. The study is expected to
be completed in FY25.
UNITS
Five priority corridors
highly prospective for gold
mineralisation identified
Heather Bore drill program
completed
16
| AERIS RESOURCES
FY2024
FY2023
Ore Mined
kt
55.2
402.6
Mined Grade
% Zn
7.05
5.95
Ore Milled
kt
66.8
432.6
Milled Grade
% Zn
5.92
5.97
Recovery
% Zn
78.2
87.1
Zinc Produced
kt
3.1
22.5
Copper Produced
kt
0.6
3.1
Gold Produced
koz
0.4
3.0
Silver Produced
koz
84
718
EXPLORATION
During the year, an updated MRE was completed on the Jaguar deposit based on an updated geological
interpretation. The updated Jaguar deposit MRE totals 840kt @ 2.28% Cu, 4.66% Zn and 61g/t Ag, for
19kt Cu metal, 39kt Zn metal and 1.65Moz Ag metal8.
Significant potential remains to increase the Jaguar mineralised footprint with further drilling, most notably down-plunge
from the current Mineral Resource. In addition, there is potential to define mineralisation along two parallel favourable
stratigraphic horizons, one of which contains the mined “Farside” copper sulphide lens.
2023 JAGUAR DEPOSIT MINERAL RESOURCE ESTIMATE
Resource
Category
Cut-off
grade
Tonnage
(kt)
Cu
(%)
Zn
(%)
Ag
(g/t)
Cu metal
(kt)
Zn metal
(kt)
Ag metal
(koz)
260
2.26
3.82
56
6
10
465
480
2.41
5.79
73
12
28
1,140
Inferred
100
1.70
1.26
16
2
1
50
Total
840
2.28
4.66
61
19
39
1,650
Measured
Indicated
$100 NSR
Notes:
1. Refer to ASX announcement “Correction – Jaguar Deposit Mineral Resource Update” dated 12th July 2023
2. M
r John Hamill MAusIMM MAIG CP (Geo) takes Competent Person responsibility for this Mineral Resource Estimate in accordance with
the JORC Code (2012)
3. T he cut-off grade applied to the Jaguar deposit MRE has been derived from the Net Smelter Return (NSR) calculations applied to the
Bentley deposit.
4. T he Competent Person considers that the Mineral Resource has reasonable prospects for eventual economic extraction at the cut-off
grade specified and a selective underground mining method.
5. Numbers may not sum due to rounding.
The Jaguar exploration tenement
• Heather Bore Shear - a 12km
• Pterodactyl – South Possie Well –
package is also highly prospective for
structure sub-parallel to the terrane
a 10km orogenic structure with
gold mineralisation. The regional gold
bounding Ockerberry fault and
a significant gold, arsenic and
endowment is in excess of 25Moz,
along strike from the Thunderbox
antimony anomalous geochemical
with several multi-million ounce
deposit, which includes the 2km
signature and includes the
deposits located within 50km of the
long shallow gold anomaly at the
Pterodactyl prospect, which has a
Jaguar tenement package.
Heather Bore prospect.
historical drill intersection reporting
A strategic review of the tenement
• Aesop – Halloween Trend – a 6km
35m @ 1.00 g/t Au.
package identified five priority
structural corridor associated with
• Southern Boundary - the interpreted
corridors considered highly
a brecciated magnetite-hematite-
extension of the Pterodactyl – South
prospective for gold mineralisation:
pyrite altered porphyry intrusion
Possie Well favourable geological
with limited historical drilling
setting to the southern tenement
and surface sampling reporting
boundary.
numerous +0.5g/t Au intervals.
• Granite Margin Domain - Structural
complexity within and along the
margins of large granite bodies.
8. Refer to ASX announcement “Correction - Jaguar Deposit Mineral Resource Update” dated 12th July 2023
2024 ANNUAL REPORT
|
17
Plan view of the Jaguar Operation tenement package highlighting areas prospective for gold mineralisation
denoted by shaded orange corridors
18
|
AERIS RESOURCES
A two-hole diamond drill program was completed at the Heather Bore prospect late in FY24. The program was designed
to test for the presence of primary gold mineralisation in fresh rock below an extensive, shallow +0.5g/t gold anomaly in
the weathered rock profile. Results from the drilling are expected in FY25.
2024 ANNUAL REPORT
|
19
STOCKMAN PROJECT
Feasibility studies and
permitting activities continued
Metallurgical test work
delivered improved metal
recoveries
Robust, simplified plan
developed to mine from
Currawong deposit for first
12 years
Updated Mineral Resources
Estimates for Currawong and
Wilga deposits
At the Stockman Project, feasibility study and permitting activities
continued in FY24. A robust mine plan has been developed involving
+12 years of ore production from the single Currawong deposit at a
mining rate of 850ktpa9.
The metallurgy of the Stockman
metal products. Initial test work has
deposits is complex and impacts
demonstrated high recoveries of
metal recovery and processing costs
metal into the copper concentrate
through a standard flotation circuit.
and bulk concentrate and through
Aeris is investigating the feasibility
the Albion process leaching.
of introducing the Albion oxidative
leach process to the flowsheet to
provide a step change in recoveries.
Work continues on detailed
metallurgical testing and engineering
studies for the revised processing
The revised processing route will
flowsheet. The feasibility study is
incorporate onsite production of a
expected to be completed in FY25.
clean copper concentrate for sale
and a bulk Cu/Zn/Au/Ag concentrate
for further processing. The bulk
concentrate is to be trucked to a
regional offsite location with access
to lower cost power for treatment
through the Albion process into
saleable copper, zinc and precious
During the year, Aeris also released
an updated MRE for the Currawong
and Wilga deposits at the Stockman
Project. The updated resource
increased total tonnes by 7% and
contained copper by 6% from the
previous estimate10.
9. R
efer to ASX announcement “Stockman Feasibility Study Update” dated 24 January 2024 for more information and for the material
assumptions underpinning the production target
10. Refer to ASX announcement “Stockman Project – Currawong and Wilga Deposits Mineral Resource Update” dated 17 January 2024
20
|
AERIS RESOURCES
Currawong mine design
2024 ANNUAL REPORT
|
21
Resources
and Reserves
The Mineral Resource and Ore Reserve estimates are
reported in accordance with the guidelines of the
2012 Edition of the Australasian Code for Reporting
of Exploration Results, Mineral Resources and Ore
Reserves (“JORC 2012”). The estimates are reported
at 31 December 2023.
22
|
AERIS RESOURCES
MINERAL RESOURCE ESTIMATES
Base Metals
Project
Tritton
Jaguar
North Qld
Grade
Category
Measured
Group
Tonnes
Cu
Zn
Au
Ag
Cu
Zn
Au
Ag
(‘000)
(%)
(%)
(g/t)
(g/t)
(kt)
(kt)
(koz)
(koz)
1,300
1.0
-
0.1
3
13
-
4
120
Indicated
11,200
1.3
-
0.3
4
145
-
91
1,280
Inferred
10,000
1.8
-
0.4
5
183
-
137
1,440
Total
22,500
1.5
-
0.3
4
342
-
232
2,840
Measured
500
1.6
5.0
0.3
63
8
25
4
1,030
Indicated
3,400
1.3
7.6
0.5
75
45
256
51
8,170
Inferred
4,000
1.2
4.0
0.5
56
47
161
68
7,270
Total
7,900
1.3
5.6
0.5
65
100
442
123
16,460
Measured
300
2.8
-
0.6
-
9
-
6
-
Indicated
2,200
2.0
-
0.2
3
44
-
13
210
Inferred
600
2.0
-
0.1
2
11
-
2
30
Total
Stockman
3,100
2.1
-
0.2
2
65
-
21
240
Measured
-
-
-
-
-
-
-
-
-
Indicated
13,400
2.1
4.2
1.0
37
288
561
420
16,000
Inferred
2,400
1.1
2.6
1.5
32
27
62
117
2,440
Total
15,800
2.0
4.0
1.1
36
315
623
537
18,450
Total Measured
2,100
1.4
1.2
0.2
17
31
25
14
1,150
Total Indicated
30,200
1.7
2.7
0.6
26
524
817
576
25,660
Total Inferred
16,900
1.6
1.3
0.6
21
268
223
323
11,190
Grand Total
49,300
1.7
2.2
0.6
24
822
1,065
913
37,990
Gold
Project
Cracow
Contained Metal
Grade
Category
Contained Metal
Tonnes
Cu
Zn
Au
Ag
Cu
Zn
Au
Ag
(‘000)
(%)
(%)
(g/t)
(g/t)
(kt)
(kt)
(koz)
(koz)
Measured
400
-
-
3.9
3
-
-
52
39
Indicated
2,100
-
-
3.4
4
-
-
259
249
Inferred
2,400
-
-
2.9
4
-
-
208
376
Grand Total
4,900
-
-
3.4
4
-
-
519
664
Notes:
Mineral Resource figures are reported using a variety of cut-off grades (copper or gold) or NSR calculation best suited to each deposit.
Discrepancy in summation may occur due to rounding.
2024 ANNUAL REPORT
|
23
ORE RESERVE ESTIMATES
Base Metals
Project
Tritton
Jaguar
North Qld
Stockman
Group
Grade
Category
Cu
Zn
Au
Ag
Cu
Zn
Au
Ag
(‘000)
(%)
(%)
(g/t)
(g/t)
(kt)
(kt)
(koz)
(koz)
5
1.8
-
-
-
0.1
-
-
-
Probable
2,790
1.5
-
0.3
5
41
-
23
451
Total
2,790
1.5
-
0.3
5
41
-
23
451
Proved
90
1.4
8.7
0.8
74
1
8
2
225
Probable
1,060
1.4
8.3
0.6
45
16
87
21
1,534
Total
1,150
1.5
8.3
0.6
48
17
95
23
1,759
Proved
Proved
90
2.4
-
0.5
-
2
-
1
-
Probable
80
2.1
-
0.4
-
2
-
1
-
Total
170
2.3
-
0.4
-
2
-
2
-
-
-
-
-
-
-
-
-
-
Probable
Proved
9,640
1.9
4.3
1.0
36
183
413
318
11,409
Total
9,640
1.9
4.3
1.0
36
183
413
318
11,409
190
1.9
4.4
0.6
37
3
8
4
225
Total Probable
Total Proved
13,560
1.8
3.7
0.8
30
242
500
363
13,394
Grand Total
13,750
1.8
3.7
0.8
30
245
508
367
13,619
Gold
Project
Cracow
Contained Metal
Tonnes
Grade
Category
Contained Metal
Tonnes
Cu
Zn
Au
Ag
Cu
Zn
Au
Ag
(‘000)
(%)
(%)
(g/t)
(g/t)
(kt)
(kt)
(koz)
(koz)
Proved
100
-
-
3.5
-
-
-
12
-
Probable
250
-
-
3.4
-
-
-
28
-
Grand Total
360
-
-
3.4
-
-
-
39
-
Notes:
Ore Reserve figures are reported using a variety of cut-off criteria suitable for each deposit.
Discrepancy in summation may occur due to rounding.
The Jaguar Ore Reserve has not been updated since the previous reporting period (end December 2022). Operations were suspended
at Jaguar in September 2023 and the mine placed on care and maintenance pending restart studies (refer to ASX Release “Corporate
Update and FY24 Guidance” 2 Aug 2023). Production in 2023 was 233kt @1.2% Cu, 4.5% Zn, 0.6g/t Au & 52g/t Ag. Ore Reserve depletion
over the same period was 113kt @ 1.4% Cu, 7.3% Zn, 0.8g/t Au & 78g/t Ag.
24
| AERIS RESOURCES
SUMMARY OF COMPETENT PERSONS FOR MINERAL RESOURCE AND ORE RESERVE ESTIMATES
Asset
Competent Person
Qualifications
Membership
Angela Dimond
BSc (Hons)
MAusIMM
Constellation
Brad Cox
BSc (Hons)
MAusIMM
Kurrajong
Andrew Fowler
PhD
MAusIMM
Tim Brettell
BEng
MAusIMM
Cam Schubert
BSc (Hons), MEngSc,
FAusIMM
TRITTON OPERATIONS
Mineral Resource
Tritton
Murrawombie
Budgerygar
Avoca Tank
Budgery
Ore Reserve
Tritton
Budgerygar
Avoca Tank
Murrawombie
Underground
Murrawo